Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

DEPOSIT-WORK-KRFB-KIIFB-Improvements to Kecheri - Akkikavu Bypass road-Utility Shifting-Laying various size of pipe line

Project DEPOSIT-WORK-KRFB-KIIFB-Improvements to Kecheri - Akkikavu Bypass road-Utility Shifting-Laying various size of pipe line
Project Code TCRDEPO092213998
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-WORK-KRFB-KIIFB-Improvements to Kecheri - Akkikavu Bypass road-Utility Shifting-Laying various size of pipe line
Status On-going
District Thrissur
Executing Office Thrissur PH Dn
AS Amount (Rs) 38838000
AS Number KAB/03/KRFB*PMU/EKM-TSR/2021
TS Amount (Rs) 9660000
TS Number WRD/KWA-CE(CR)/EST_TS/17175/2022
Total Bill Submitted (Rs) 5040830
Total Bill Paid (Rs) 5040830
Population Benefitted 4500
Capacity in MLD 1.00
Actual Project Completion Date Date is not specified
Coverage Kecheri - Akkikavu Bypass road
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 DEPOSIT-WORK-KRFB-KIIFB-Improvements to Kecheri - Akkikavu Bypass road -Utility Shifting Laying Various size of Pipe ine - Part 3-Pipeline Work Kunnamkulam Sn
2 DEPOSIT-WORK-KRFB-KIIFB-Improvements to Kecheri - Akkikavu Bypass road-Utility Shifting-Laying various size of pipe line - part 2-Pipeline Work Kunnamkulam Sn
3 DEPOSIT-WORK-KRFB-KIIFB-Improvements to Kecheri-Akkikkavu Byepass road -Utility shifting Laying various size of pipe line - Part 1-Pipeline Work-1 Kunnamkulam Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 May 2024 Part 1-Pipe laying work completed .Inter connection , charging and commissioning work pending -90% part 2-Pipe laying work completed.Inter connection ,charging and commissioning work pending 90% Part 3-Work ongoing,Pipe laying work completed.Inter connection,charging and commissioning work pending reinstallation of existing connection pending 90% Kunnamkulam PH Sn - AE
17 May 2024 Part 1-Pipe laying work completed .Inter connection , charging and commissioning work pending -90% part 2-Pipe laying work completed.Inter connection ,charging and commissioning work pending 90% Part 3-Work ongoing,Pipe laying work completed.Inter connection,charging and commissioning work pending reinstallation of existing connection pending 90% Kunnamkulam PH Sn - AE
16 May 2024 Part 1-Pipe laying work completed .Inter connection , charging and commissioning work pending -90% part 2-Pipe laying work completed.Inter connection ,charging and commissioning work pending 90% Part 3-Work ongoing,Pipe laying work completed.Inter connection,charging and commissioning work pending reinstallation of existing connection pending 90% Kunnamkulam PH Sn - AE
15 May 2024 Part 1-Pipe laying work completed .Inter connection , charging and commissioning work pending -90% part 2-Pipe laying work completed.Inter connection ,charging and commissioning work pending 90% Part 3-Work ongoing,Pipe laying work completed.Inter connection,charging and commissioning work pending reinstallation of existing connection pending 90% Kunnamkulam PH Sn - AE
14 May 2024 Part 1-Pipe laying work completed .Inter connection , charging and commissioning work pending -90% part 2-Pipe laying work completed.Inter connection ,charging and commissioning work pending 90% Part 3-Work ongoing,Pipe laying work completed.Inter connection,charging and commissioning work pending reinstallation of existing connection pending 90% Kunnamkulam PH Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 17/02/2023
Scheduled date of Completion of the Project 24 Jun 2023
Expected date of Completion 31/05/2024

Processing Dates

AS Date 03 Sep 2022
TS Date 27 Jan 2023

Other details

Project Officers View