Project | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Puzhathi Zone I |
---|---|
Project Code | KNRAMRUT122315862P1 |
Type | Package |
Main Project | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Puzhathi Zone I |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | AMRUT |
Description | AMRUT 1.0-Kannur Corporation-pipeline extension, providing water connections in various zones of Kannur Corporation-Phase II-Puzhathi Zone I |
Status | On-going |
District | Kannur |
Executing Office | Kannur WS Sn 3 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 43600000 |
TS Number | 23770/2023-24 |
Technical specification | 90mm PVC 8kg/cm2 pipe ,110mm PVC 8kg/cm2 pipe, 160mm PVC 8kg/cm2 pipe |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/02/2024 |
---|---|
Scheduled date of Completion as per agreement | 12 Apr 2024 |
Expected date of Completion | 12/04/2024 |
TS Date | 08 Jan 2024 |
---|---|
Estimate Approval | 02 Jan 2024 |
NIT Approval | 08 Jan 2024 |
Tender Closing | 15 Jan 2024 |
Technichal Pre-Qualification | 08 Jan 2024 |
Price bid opening | 16 Jan 2024 |
Workorder Date | 01 Feb 2024 |
---|---|
NA | 15 Feb 2024 |
Kannur PH Sn 3 AE |
Date: 30/06/2025 |
Work in progress | 90% Completed
9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km.
Kannur PH Sn 3 AE |
Date: 27/06/2025 |
Work in progress | 90% Completed
9.6 KM pipe laid 890 nos FHTC given. Road restoration-3.4km.