Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

DEPOSIT-District panchayath Deposit work : pipe line extension at vasudevapuram road myvalliela -project no 437/22 {ward no:4}in mudakkal panchayath-Pipeline Work

Project DEPOSIT-District panchayath Deposit work : pipe line extension at vasudevapuram road myvalliela -project no 437/22 {ward no:4}in mudakkal panchayath-Pipeline Work
Project Code TVMDEPO062112772
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description pipe line extension at vasudevapuram road myvalliela -project no 437/22 {ward no:4}in mudakkal panchayath-Pipeline Work
Status Completed
District Thiruvananthapuram
Executing Office Attingal WS Sn 2
AS Amount (Rs) 300000
AS Number HD1/EE/LID&EW/2020-21
TS Amount (Rs) 300000
TS Number TS/2021-2022/2021/39597
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 60
Capacity in MLD 0.10
Actual Project Completion Date 28 Feb 2023
Coverage pipe line extension at vasudevapuram road myvalliela -project no 437/22 {ward no:4}in mudakkal panchayath
Work Plan Download

Packages

No. Project Name Location View
1 DEPOSIT-District panchayath Deposit work : pipe line extension at vasudevapuram road myvalliela -project no 437/22 {ward no:4}in mudakkal panchayath-Pipeline Work Attingal WS Sn 2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Feb 2023 work completed Attingal WS Sn no 2 - AE
28 Jan 2023 pipe laying started Attingal WS Sn no 2 - AE
07 Dec 2022 Agreement Executed on 6/12/2022 Attingal WS SDn - AEE
02 Dec 2022 Work order issued on 01/12/2022 Attingal WS Sn no 2 - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/12/2022
Scheduled date of Completion of the Project 28 Feb 2023
Expected date of Completion 21/02/2023

Processing Dates

AS Date 22 Jun 2021
TS Date 10 Nov 2022

Other details

Project Officers View