State Plan-2020-21-TSS –Reconstruction of old dilapidated rick manholes with R C C and Raising of manhole covers in the West R C area under Sewerage Section , Sasthamangalam.
Project |
State Plan-2020-21-TSS –Reconstruction of old dilapidated rick manholes with R C C and Raising of manhole covers in the West R C area under Sewerage Section , Sasthamangalam. |
Project Code |
TVMGOK10204327 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
TSS –Reconstruction of old dilapidated brick manholes with R C C and Raising of manhole covers in the West R C area under Sewerage Section , Sasthamangalam. |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Sasthamangalam Sewerage Sn |
AS Amount (Rs) |
4018000
|
AS Number |
KWA/JB/P4/9/2020-2021 |
TS Amount (Rs) |
4017000 |
TS Number |
10334/2020-2021 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
10000 |
Capacity in MLD |
0.01 |
Actual Project Completion Date |
16 Oct 2021 |
Coverage |
Reconstruction of old dilapidated brick manholes with R C C and Raising of manhole covers in the West R C area under Sewerage Section , Sasthamangalam. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
State Plan-2020-21-TSS –Reconstruction of old dilapidated rick manholes with R C C and Raising of manhole covers in the West R C area under Sewerage Section , Sasthamangalam. |
Sasthamangalam Sewerage Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
24 Nov 2021 |
Edassery lane kumarapuram road restoration on completed |
Sasthamangalam Sewerage Sn AE |
|
20 Nov 2021 |
Edassery lane kumarapuram road restoration on progress |
Sasthamangalam Sewerage Sn AE |
|
16 Nov 2021 |
MH Raising progress at kumarapuram area 87% completed |
Sasthamangalam Sewerage Sn AE |
|
08 Nov 2021 |
manhole reconstruction Completed at Edassery lane kumarapuram 81% completed |
Sasthamangalam Sewerage Sn AE |
|
03 Nov 2021 |
manhole reconstruction started at Edassery lane kumarapuram 80% completed |
Sasthamangalam Sewerage Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
04/01/2021 |
Scheduled date of Completion of the Project |
16 Oct 2021 |
Expected date of Completion |
30/11/2021 |
Processing Dates
AS Date |
08 Oct 2020 |
TS Date |
02 Nov 2020 |