Deposit work: Kozhikode Block Panchayath (SC Development fund) KWA Pipe Extension and Providing Domestic Water Connection to Households of Ambedkar Gramam (SC Colony ) in Ramanatukara Municipality.

Project Deposit work: Kozhikode Block Panchayath (SC Development fund) KWA Pipe Extension and Providing Domestic Water Connection to Households of Ambedkar Gramam (SC Colony ) in Ramanatukara Municipality.
Project Code CLTDEPO032211277
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work: Kozhikode Block Panchayath (SC Development fund) KWA Pipe Extension and Providing Domestic Water Connection to Households of Ambedkar Gramam (SC Colony ) in Ramanatukara Municipality.
Status Completed
District Kozhikkode
Executing Office Kozhikode RWS Sub Dn
AS Amount (Rs) 700000
AS Number KDNK/P1086/219/2018
TS Amount (Rs) 680000
TS Number 2117/2022-2023
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 126
Capacity in MLD 174.00
Actual Project Completion Date 02 Dec 2022
Coverage Deposit work: Kozhikode Block Panchayath (SC Development fund) KWA Pipe Extension and Providing Domestic Water Connection to Households of Ambedkar Gramam (SC Colony ) in Ramanatukara Municipality.

Packages

No. Project Name Location View
1 Deposit work: Kozhikode Block Panchayath (SC Development fund) KWA Pipe Extension and Providing Domestic Water Connection to Households of Ambedkar Gramam (SC Colony ) in Ramanatukara Municipality. Beypore RWS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Dec 2022 Completed Kozhikode PH Dn EE
24 Nov 2022 Work in progress Kozhikode PH Dn EE
22 Nov 2022 Work in progress Kozhikode PH Dn EE
22 Nov 2022 Work in progress Kozhikode PH Dn EE
12 Oct 2022 Work in progress Kozhikode PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 01/07/2022
Scheduled date of Completion of the Project 19 Nov 2022
Expected date of Completion 30/11/2022

Processing Dates

AS Date 04 Mar 2022
TS Date 28 Apr 2022

Other details

Project Officers View