Deposit-ITDP-WSS to Paroorkunnu colony- Soil investigation work

Project Deposit-ITDP-WSS to Paroorkunnu colony- Soil investigation work
Project Code WYDITDP032417045P1
Type Package
Main Project Deposit-ITDP-WSS to Paroorkunnu colony- Soil investigation work
Funding Agency ITDP
Category Deposit Work
Type of scheme Water Supply
Scheme Tribal Department
Description Deposit-ITDP-WSS to Paroorkunnu colony- Soil investigation work
Status On-going
District Wayanad
Executing Office Sulthan Bathery Sn
Agreement Number
Agreement Date
TS Amount (Rs) 160000
TS Number TS/20832/2024_3_1_1
Technical specification

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/12/2024
Scheduled date of Completion as per agreement 17 Jan 2025
Expected date of Completion 17/01/2025

Processing Dates

TS Date 10 Dec 2024
Estimate Approval 10 Dec 2024

Approval Dates

Workorder Date 18 Dec 2024
NA 18 Dec 2024

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Sulthan Bathery PH Dn EE
Date: 07/01/2025

Work in progress | 1% Completed

Agreement Executed on 18.12.2024.