JAL JEEVAN MISSION- 2020-21- WSS to Vadakarapathy and Eruthenpathy panchayaths - Supplying, laying, testing, commissioning and maintenance of balance distribution systems and providing FHTCs (354Nos) in Palakkad district -
JAL JEEVAN MISSION- 2020-21- WSS to Vadakarapathy and Eruthenpathy panchayaths - Supplying, laying, testing, commissioning and maintenance of balance distribution systems and providing FHTCs (354Nos) in Palakkad district -
Project Code
PKDJJM082113632
Type
Main project
Funding Agency
JJM
Category
JJM
Type of scheme
Water Supply
Scheme
4215-01-102-92-02
Description
JAL JEEVAN MISSION- 2020-21- WSS to Vadakarapathy and Eruthenpathy panchayaths - Supplying, laying, testing, commissioning and maintenance of
balance distribution systems and providing FHTCs (354Nos) in Palakkad
district -
Status
On-going
District
Palakkad
Executing Office
Chittur Project Dn
AS Amount (Rs)
717000000
AS Number
GO(RT) NO.541/2020/WRD
TS Amount (Rs)
33400000
TS Number
WRD/KWA-CE(NR)EST/TS/2334/2022/DTD 23.11.2022
Total Bill Submitted (Rs)
5391197
Total Bill Paid (Rs)
5391197
Population Benefitted
95472
Capacity in MLD
8.00
Actual Project Completion Date
Date is not specified
Coverage
Kozhinjampara,vadakarapathy,eruthempathy
Packages
No.
Project Name
Location
View
1
JAL JEEVAN MISSION- 2020-21- WSS to Vadakarapathy and Eruthenpathy panchayaths - Supplying, laying, testing, commissioning and maintenance of balance distribution systems and providing FHTCs (354Nos) in Palakkad district -
Project Division Chittur
Overall Project Status
Status Date
Overall Project Status
Project Officer
Contact
24 Jan 2024
Work in progress | 99% Completed | 24/01/2024
100% work completed
Total 25km laid/22 km , fhtc738/354 nos(fhtc excess provided) VADAKARAPATHY- 10KM, ERUTHEMPATYHY-15 KM 1.) 90MM PVC 6 KG- 13.279M LAID/out of 22km, 2). 147 FHTC provided/354 nos 3)90mm pvc 8 kg-720m laid
Chittur Project Dn - AE 4
01 Dec 2023
Work in progress | 71% Completed | 01/12/2023
Total 15.204km laid/22 km , VADAKARAPATHY- 4.331KM, ERUTHEMPATYHY-9.736 KM 1.) 90MM PVC 6 KG- 13.279M LAID/out of 22km, 2). 147 FHTC provided/354 nos 3)90mm pvc 8 kg-720m laid
Chittur Project Dn - AE 4
31 Oct 2023
Work in progress | 71% Completed | 31/10/2023
Total 15.204km laid/22 km , VADAKARAPATHY- 4.331KM, ERUTHEMPATYHY-9.736 KM 1.) 90MM PVC 6 KG- 13.279M LAID/out of 22km, 2). 147 FHTC provided/354 nos 3)90mm pvc 8 kg-720m laid
Chittur Project Dn - AE 4
13 Oct 2023
Work in progress | 71% Completed | 13/10/2023
Total 15.204km laid/22 km , VADAKARAPATHY- 4.331KM, ERUTHEMPATYHY-9.736 KM 1.) 90MM PVC 6 KG- 13.279M LAID/out of 22km, 2). 147 FHTC provided/354 nos 3)90mm pvc 8 kg-720m laid
Chittur Project Dn - AE 4
30 Sep 2023
Work in progress | 71% Completed | 30/09/2023
Total 15.204km laid/22 km , VADAKARAPATHY- 4.331KM, ERUTHEMPATYHY-9.736 KM 1.) 90MM PVC 6 KG- 13.279M LAID/out of 22km, 2). 147 FHTC provided/354 nos 3)90mm pvc 8 kg-720m laid