- Home
- Annual Mace 2022-23 - RWSS to Chittar-Me...
Annual Mace 2022-23 - RWSS to Chittar-Meenkuzhy-Kodumudy - Leak rectification works to pipe line in Chittar Grama Panchayath
| Project |
Annual Mace 2022-23 - RWSS to Chittar-Meenkuzhy-Kodumudy - Leak rectification works to pipe line in Chittar Grama Panchayath |
| Project Code |
PTADEPO042211348 |
| Type |
Main project |
| Funding Agency |
DEPO |
| Category |
Deposit Work |
| Type of scheme |
Water Supply |
| Scheme |
DEPO |
| Description |
Annual Mace 2022-23 - RWSS to Chittar-Meenkuzhy-Kodumudy - Leak rectification works to pipe line in Chittar Grama Panchayath |
| Status |
Dropped |
| District |
Pathanamthitta |
| Executing Office |
Ranni Sub Dn |
| AS Amount (Rs) |
738500
|
| AS Number |
TS_MAINTENANCE/2022/14467 |
| TS Amount (Rs) |
738500 |
| TS Number |
TS/2022-2023/2022/14467 |
| Total Bill Submitted (Rs) |
|
| Total Bill Paid (Rs) |
|
| Population Benefitted |
|
| Capacity in MLD |
|
| Actual Project Completion Date |
Date is not specified |
| Coverage |
|
Packages
| No. |
Project Name |
Location |
View |
| 1 |
Annual Mace 2022-23 - RWSS to Chittar-Meenkuzhy-Kodumudy - Leak rectification works to pipe line in Chittar Grama Panchayath |
Ranni Sub Dn |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
| Date of start of Project |
02/06/2022 |
| Scheduled date of Completion of the Project |
02 Sep 2022 |
| Expected date of Completion |
02/09/2022 |
Processing Dates
| AS Date |
30 Apr 2022 |
| TS Date |
30 Apr 2022 |