- Home
- Planning and Economic Affairs (RKI) Depa...
Planning and Economic Affairs (RKI) Department- Project proposal from KWA-Topographical survey & DPR preparation of additional 7 ULBs for implementation of sewerage scheme.
Project |
Planning and Economic Affairs (RKI) Department- Project proposal from KWA-Topographical survey & DPR preparation of additional 7 ULBs for implementation of sewerage scheme. |
Project Code |
TVMRKI092213717 |
Type |
Main project |
Funding Agency |
RKI |
Category |
RKI |
Type of scheme |
Water Supply |
Scheme |
5475-00-115-94-05 |
Description |
Planning and Economic Affairs (RKI) Department- Project
proposal from KWA-Topographical survey & DPR preparation of
additional 7 ULBs for implementation of sewerage scheme. |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
PPD & Sewerage CE Office |
AS Amount (Rs) |
3116590
|
AS Number |
G.O.(Rt)No.378/2022/P&EA |
TS Amount (Rs) |
3093304 |
TS Number |
10 individual TS issued for the works mentioned in the sub components. |
Total Bill Submitted (Rs) |
2012100 |
Total Bill Paid (Rs) |
1376006 |
Population Benefitted |
280000 |
Capacity in MLD |
25.00 |
Actual Project Completion Date |
31 Mar 2023 |
Coverage |
For conducting survey works for prparing DPRs for providing
sewerage/septage coverage for the 7 ULBs. i.e at Attingal,
Nedumangadu, Karunagappally, Kalamassery, Harippad, Shornur,
Mannarkad in Thiruvananthapuram, Kollam, Kochi, Alppuzha and palakkad districts in Kerala. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Soil Investigation in Haripad Municipality in Alappuzha District. |
PPD & Sewerage CE Office |
|
2 |
Soil Investigation in Kalamassery Municipality in Kochi District. |
PPD & Sewerage CE Office |
|
3 |
Topographical Survey in Attingal Municipality in Thiruvananthapuram district. |
PPD & Sewerage CE Office |
|
4 |
Topographical Survey in Haripad Municipality in Alappuzha District. |
PPD & Sewerage CE Office |
|
5 |
Topographical Survey in Kalamassery Municipality in Kochi District. |
PPD & Sewerage CE Office |
|
6 |
Topographical Survey in Karunagapally Municipality in Kollam District. |
PPD & Sewerage CE Office |
|
7 |
Topographical Survey in Mannarkkad Municipality in Palakkad District. |
PPD & Sewerage CE Office |
|
8 |
Topographical Survey in Nedumangad Municipality in Thiruvananthapuram District. |
PPD & Sewerage CE Office |
|
9 |
Topographical Survey in Nedumangad Municipality in Thiruvananthapuram District.(Extended areas 22Km). |
PPD & Sewerage CE Office |
|
10 |
Topographical Survey in Shornur Municipality in Palakkad District. |
PPD & Sewerage CE Office |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Aug 2023 |
For the newly allotted 7 ULBs, survey works are completed. Bills amounting to Rs.20.12 lakhs- submitted for the newly allotted 7ULBs. |
Kayamkulam PH Dn - TA |
|
05 Apr 2023 |
For the newly allotted 7 ULBs, survey works are completed. Bills amounting to Rs.20.12 lakhs- submitted for the newly allotted 7ULBs. |
Kayamkulam PH Dn - TA |
|
14 Mar 2023 |
For the newly allotted 7 ULBs, survey works are completed. Bills amounting to Rs.20.12 lakhs- submitted for the newly allotted 7ULBs. |
Kayamkulam PH Dn - TA |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
28/09/2022 |
Scheduled date of Completion of the Project |
10 Mar 2023 |
Expected date of Completion |
31/03/2023 |