Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative- Njeezhoor Panchayath - Theradimala pump house under PH Section Peruva

Project Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative- Njeezhoor Panchayath - Theradimala pump house under PH Section Peruva
Project Code KTMRKI03229873
Type Main project
Funding Agency RKI
Category RKI
Type of scheme Water Supply
Scheme 5475-00-115-94-05
Description Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative- Njeezhoor Panchayath - Theradimala pump house under PH Section Peruva
Status Completed
District Kottayam
Executing Office Peruva Sn
AS Amount (Rs) 20100000
AS Number 6296/AE1(Operations)/2022/KWA/Dated 15/03/2022
TS Amount (Rs) 188000
TS Number ORDER No. TS/2022-2023/2022/14648Dated: 12-04-2022
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 400
Capacity in MLD 45.00
Actual Project Completion Date 03 May 2022
Coverage Njeezhoor panchayath.
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Automation of submersible pumps in Kerala Water Authority- Implementation of Phase 1 (Stage 1 & 2), part under Rebuild Kerala Initiative- Njeezhoor Panchayath - Theradimala pump house under PH Section Peruva Peruva Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
02 Jun 2022 work completed bill submitted Kaduthuruthy Dn EE
01 Jun 2022 work completed Kaduthuruthy Dn EE
31 May 2022 work completed Kaduthuruthy Dn EE
28 May 2022 work completed Kaduthuruthy Dn EE
27 May 2022 work completed Kaduthuruthy Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 18/04/2022
Scheduled date of Completion of the Project 27 Apr 2022
Expected date of Completion 30/06/2022

Processing Dates

AS Date 15 Mar 2022
TS Date 12 Apr 2022