- Home
- Deposit work- Providing new FHTC Connect...
Deposit work- Providing new FHTC Connection from Existing line at Muttanchery Parayarukotta road at Madavoor gramapanchayath
Project |
Deposit work- Providing new FHTC Connection from Existing line at Muttanchery Parayarukotta road at Madavoor gramapanchayath |
Project Code |
CLTDEPO072212079 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work- Providing new FHTC Connection from Existing line at Muttanchery Parayarukotta road at Madavoor gramapanchayath |
Status |
Completed |
District |
Kozhikkode |
Executing Office |
Koduvally Sn |
AS Amount (Rs) |
100000
|
AS Number |
A2/171/21 |
TS Amount (Rs) |
100000 |
TS Number |
10917/2022-23 |
Total Bill Submitted (Rs) |
70965 |
Total Bill Paid (Rs) |
70965 |
Population Benefitted |
51 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
21 Sep 2022 |
Coverage |
Work in progress |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work- Providing new FHTC Connection from Existing line at Muttanchery Parayarukotta road at Madavoor gramapanchayath |
Koduvally Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 Nov 2022 |
COMPLETED |
Kodually W S section - AE |
|
22 Oct 2022 |
work all most completed |
Kodually W S section - AE |
|
14 Oct 2022 |
work all most completed |
Kodually W S section - AE |
|
12 Oct 2022 |
work all most completed |
Kozhikode PH Dn EE |
|
14 Sep 2022 |
Work in progress. |
Kozhikode PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
30/08/2022 |
Scheduled date of Completion of the Project |
21 Sep 2022 |
Expected date of Completion |
31/10/2022 |
Processing Dates
AS Date |
18 Jul 2022 |
TS Date |
20 Jul 2022 |