Jal Jeevan Mission-2020-21 – CWSS to Muthuthala, Parathur and Thiruvegappura Grama panchayaths

Project Jal Jeevan Mission-2020-21 – CWSS to Muthuthala, Parathur and Thiruvegappura Grama panchayaths
Project Code PKDJJM12207645
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description CONSTRUCTION OF 16MLD WATER TREATMENT PLANT, CONSTRUCTION OF INTAKE WELL CUM PUMP HOUSE- 12m dia, CABIN ROOM, TRANSFORMER YARD,RETAINING WALL,RAMP AND COMPOUND WALL, RAW WATER PUMPING MAIN 500MM DIA 6000M, CONSTRUCTION OF NEW BABY WELL, ELECTRICAL POWER ALLOCATION CHARGES, CONSTRUCTION OF 47 LL OHSR, - PROVIDING DISTRIBUTION SYSTEM AND FHTCs IN MUTHUTHALA,PARATHUR AND THIRUVEGAPURA PANCHAYATHS
Status On-going
District Palakkad
Executing Office Palakkad Project Dn
AS Amount (Rs) 1151900000
AS Number G.O(Rt) No 777/2020/WRD
TS Amount (Rs) 104490000
TS Number TS/2020-2021/2020/12027
Total Bill Submitted (Rs) 1041169700
Total Bill Paid (Rs) 967448300
Population Benefitted 113000
Capacity in MLD 16.00
Actual Project Completion Date 30 May 2024
Coverage Muthuthala , Paruthur, Thiruvegappura GPs
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission-2020-21 – CWSS to Muthuthala, Parathur and Thiruvegappura Grama panchayaths Project Division Palakkad

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 16 mld WTP : Clarifiers 2no, Filter house, Aerator, Raw water channels & flash mixer etc: mechanical work , painting work & Electrical works completed. Transformer erection completed. WTP compound wall completed. CW Pump house: structural work and pump erection completed. Approach road completed. 47LL OHSR: Electrical and linking work completed, painting work in progress. Intake well: Well inside cleaning work in progress, Well : Steel stair fitting work in progress. All mechanical and civil work completed, electrical work in progress, painting in progress. Baby well,& inspection chamber: completed. RW pumping main: both end linking work completed. Distribution pipe lines: Panchayath road- 317/340 km laid, PWD Road- 79.80/82.42 km laid, PWD road gape clossing. KRFB roads & PMGSY roads linking work in progress. pipe laying, interconnections, crossings, valves & chamber works, restoration works are in progress. Applied for power connection at RWPH & WTP ; HTCs (Thiruvegapura -2385/4107 , 2004 nos geo tagged, Muthuthala - 4476/4543 , 3624 nos geo tagged & Paruthur -3390/4992 , 3135 nos geo tagged,16 FHTC Palakkad Project Dn AE
10 May 2024 16 mld WTP : Clarifiers 2no, Filter house, Aerator, Raw water channels & flash mixer etc: mechanical work , painting work & Electrical works completed. Transformer erection completed. WTP compound wall completed. CW Pump house: structural work and pump erection completed. Approach road completed. 47LL OHSR: Electrical and linking work completed, painting work in progress. Intake well: Well inside cleaning work in progress, Well : Steel stair fitting work in progress. All mechanical and civil work completed, electrical work in progress, painting in progress. Baby well,& inspection chamber: completed. RW pumping main: both end linking work completed. Distribution pipe lines: Panchayath road- 317/340 km laid, PWD Road- 79.80/82.42 km laid, PWD road gape clossing. KRFB roads & PMGSY roads linking work in progress. pipe laying, interconnections, crossings, valves & chamber works, restoration works are in progress. Applied for power connection at RWPH & WTP ; HTCs (Thiruvegapura -2385/4107 , 2004 nos geo tagged, Muthuthala - 4476/4543 , 3624 nos geo tagged & Paruthur -3390/4992 , 3135 nos geo tagged,16 FHTC Palakkad Project Dn AE
09 May 2024 16 mld WTP : Clarifiers 2no, Filter house, Aerator, Raw water channels & flash mixer etc: mechanical work , painting work & Electrical works completed. Transformer erection completed. WTP compound wall completed. CW Pump house: structural work and pump erection completed. Approach road completed. 47LL OHSR: Electrical and linking work completed, painting work in progress. Intake well: Well inside cleaning work in progress, Well : Steel stair fitting work in progress. All mechanical and civil work completed, electrical work in progress, painting in progress. Baby well,& inspection chamber: completed. RW pumping main: both end linking work completed. Distribution pipe lines: Panchayath road- 317/340 km laid, PWD Road- 79.80/82.42 km laid, PWD road gape clossing. KRFB roads & PMGSY roads linking work in progress. pipe laying, interconnections, crossings, valves & chamber works, restoration works are in progress. Applied for power connection at RWPH & WTP ; HTCs (Thiruvegapura -2385/4107 , 2004 nos geo tagged, Muthuthala - 4476/4543 , 3624 nos geo tagged & Paruthur -3390/4992 , 3135 nos geo tagged,16 FHTC Palakkad Project Dn EE
06 May 2024 16 mld WTP : Clarifiers 2no, Filter house, Aerator, Raw water channels & flash mixer etc: mechanical work , painting work & Electrical works completed. Transformer erection completed. WTP compound wall completed. CW Pump house: structural work and pump erection completed. Approach road completed. 47LL OHSR: Electrical and linking work completed, painting work in progress. Intake well: Well inside cleaning work in progress, Well : Steel stair fitting work in progress. All mechanical and civil work completed, electrical work in progress, painting in progress. Baby well,& inspection chamber: completed. RW pumping main: both end linking work completed. Distribution pipe lines: Panchayath road- 317/340 km laid, PWD Road- 79.80/82.42 km laid, PWD road gape clossing. KRFB roads & PMGSY roads linking work in progress. pipe laying, interconnections, crossings, valves & chamber works, restoration works are in progress. Applied for power connection at RWPH & WTP ; HTCs (Thiruvegapura -2385/4107 , 2004 nos geo tagged, Muthuthala - 4476/4543 , 3624 nos geo tagged & Paruthur -3390/4992 , 3135 nos geo tagged,16 FHTC Palakkad Project Dn EE
03 May 2024 16 mld WTP : Clarifiers 2no, Filter house, Aerator, Raw water channels & flash mixer etc: mechanical work , painting work & Electrical works completed. Transformer erection completed. WTP compound wall completed. CW Pump house: structural work and pump erection completed. Approach road completed. 47LL OHSR: Electrical and linking work completed, painting work in progress. Intake well: Well inside cleaning work in progress, Well : Steel stair fitting work in progress. All mechanical and civil work completed, electrical work in progress, painting in progress. Baby well,& inspection chamber: completed. RW pumping main: both end linking work completed. Distribution pipe lines: Panchayath road- 317/340 km laid, PWD Road- 79.80/82.42 km laid, PWD road gape clossing. KRFB roads & PMGSY roads linking work in progress. pipe laying, interconnections, crossings, valves & chamber works, restoration works are in progress. Applied for power connection at RWPH & WTP ; HTCs (Thiruvegapura -2385/4107 , 2004 nos geo tagged, Muthuthala - 4476/4543 , 3624 nos geo tagged & Paruthur -3390/4992 , 3135 nos geo tagged,16 FHTC Palakkad Project Dn AE

Project Review

See All Review messages
Review Date Review Message Review Attended By
05 Nov 2021 Complete PWD road pipe laying work in 5 roads first as per Road Co-ordination Committe recomendations AEE,Ae

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
22 Jun 2022 Pending Pending Approval/Permissions Related (from other departments excluding road cut permission and land related) Railway crossing near Kodumunda gate -160mm pipeline- in Muthuthala Pt No comments available. Pending

Duration & Sanction dates

Date of start of Project 26/04/2021
Scheduled date of Completion of the Project 25 Oct 2022
Expected date of Completion 31/03/2024

Processing Dates

AS Date 24 Dec 2020
TS Date 04 Feb 2021

Other details

Project Officers View