Project | Deposit work - NABARD-RIDF-XXXVIII Modernisation of Azhikkal Fishery harbor providing drinking water facility - Pipeline work |
---|---|
Project Code | KNRGOK032416714P1 |
Type | Package |
Main Project | Deposit work - NABARD-RIDF-XXXVIII Modernisation of Azhikkal Fishery harbor providing drinking water facility - Pipeline work |
Funding Agency | GOK |
Category | Deposit Work |
Type of scheme | Water Supply |
Scheme | 4215-01-800-89 |
Description | Deposit work - NABARD-RIDF-XXXVIII Modernisation of Azhikkal Fishery harbor providing drinking water facility - Pipeline work |
Status | On-going |
District | Kannur |
Executing Office | Kannur WS Sn 3 |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 2100000 |
TS Number | 945/2024-2025 |
Technical specification | 160mm PVC 8kg/cm2 pipe,90mm PVC 8kg/cm2 pipe |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 20/09/2024 |
---|---|
Scheduled date of Completion as per agreement | 19 Oct 2024 |
Expected date of Completion | 30/12/2024 |
TS Date | 12 Apr 2024 |
---|---|
Estimate Approval | 26 Mar 2024 |
NIT Approval | 12 Apr 2024 |
Tender Closing | 24 Jul 2024 |
Technichal Pre-Qualification | 12 Apr 2024 |
Price bid opening | 23 Jul 2024 |
Workorder Date | 02 Sep 2024 |
---|---|
NA | 10 Sep 2024 |
Kannur PH Sn 3 AE |
Date: 30/06/2025 |
Work in progress | 50% Completed
300 m pipe laid.
Kannur PH Sn 3 AE |
Date: 27/06/2025 |
Work in progress | 45% Completed
300m pipe laid.