- Jal Jeevan mission 2021-22- Providing FHTCs to all House holds by extending pipe line in various places of different wards in Karumkulam Grama panchayath (Phase3) -
Project |
- Jal Jeevan mission 2021-22- Providing FHTCs to all House holds by extending pipe line in various places of different wards in Karumkulam Grama panchayath (Phase3) - |
Project Code |
TVMJJM092110035 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Providing FHTCs to all House holds by extending pipe line in various places of different wards in Karumkulam Grama panchayath (phase-3) and giving 4657 FHTC to HH and laying 90mm HDPE pipe 20000 m, 110mm HDPE 10000m and 32mm pipe 5000m etc and Providing VT pump set at Thirupuram RWPH and CF pump set at Kumily WTP -PROVIDING INTER CONNECTION FROM NEWLY CONSTRUCTED OHSR AT PARANIYAM AND RELATED WORKS |
Status |
On-going |
District |
Thiruvananthapuram |
Executing Office |
Kanjiramkulam WS Sub Dn |
AS Amount (Rs) |
104700000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
91500000 |
TS Number |
. TS/2021-2022/2021/3499 |
Total Bill Submitted (Rs) |
59900000 |
Total Bill Paid (Rs) |
65160000 |
Population Benefitted |
18268 |
Capacity in MLD |
2.74 |
Actual Project Completion Date |
23 Dec 2022 |
Coverage |
Karumkulam Panchayat all wards |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
- Jal Jeevan mission 2021-22- Providing FHTCs to all House holds by extending pipe line in various places of different wards in Karumkulam Grama panchayath (Phase3) - |
Kanjiramkulam WS Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
19 Mar 2024 |
FHTC given to available house holds, as directed by the panchayat waiting for the completion of life mission houses |
Kanjiramkulam AE JJM |
|
11 Mar 2024 |
FHTC given to available House Holds |
Kanjiramkulam AE JJM |
|
05 Mar 2024 |
FHTC given to available house holds, as directed by the panchayat waiting for the completion of life mission houses |
Kanjiramkulam AE JJM |
|
01 Mar 2024 |
FHTC given to available house holds, |
Kanjiramkulam AE JJM |
|
22 Feb 2024 |
FHTC given to available house holds, as directed by the panchayat waiting for the completion of life mission houses |
Kanjiramkulam AE JJM |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/04/2022 |
Scheduled date of Completion of the Project |
23 Dec 2022 |
Expected date of Completion |
30/03/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
18 Nov 2021 |