: Deposit work - Karunagappaliy Municipality - CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension and interconnection of distribution pipe line with 75 mm PVC CL3 pipe from Thondappuram Palam to Munduthara jn. in Division - 1 of Karunagappaliy Municipality.

Project : Deposit work - Karunagappaliy Municipality - CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension and interconnection of distribution pipe line with 75 mm PVC CL3 pipe from Thondappuram Palam to Munduthara jn. in Division - 1 of Karunagappaliy Municipality.
Project Code KLMDEPO072212383
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description : Deposit work - Karunagappaliy Municipality - CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension and interconnection of distribution pipe line with 75 mm PVC CL3 pipe from Thondappuram Palam to Munduthara jn. in Division - 1 of Karunagappaliy Municipality.
Status Completed
District Kollam
Executing Office Chavara PH Sub Dn
AS Amount (Rs) 225000
AS Number RBI0812270211590
TS Amount (Rs) 22500
TS Number 9436/2022-2023
Total Bill Submitted (Rs) 1
Total Bill Paid (Rs) 1
Population Benefitted
Capacity in MLD 15.00
Actual Project Completion Date Date is not specified
Coverage
Work Plan Download

Packages

No. Project Name Location View
1 : Deposit work - Karunagappaliy Municipality - CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension and interconnection of distribution pipe line with 75 mm PVC CL3 pipe from Thondappuram Palam to Munduthara jn. in Division - 1 of Karunagappaliy Municipality. Oachira PH Sn
2 : Deposit work - Karunagappaliy Municipality - CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension and interconnection of distribution pipe line with 75 mm PVC CL3 pipe from Thondappuram Palam to Munduthara jn. in Division - 1 of Karunagappaliy Municipality. Chavara PH Sub Dn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
01 Feb 2023 Work Completed, Bill submitted on 23.11.2022 Oachira AE
31 Jan 2023 Work Completed, Bill submitted on 23.11.2022 Oachira AE
17 Oct 2022 Work completed Oachira AE
14 Oct 2022 Work completed Oachira AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/08/2022
Scheduled date of Completion of the Project 19 Sep 2022
Expected date of Completion Date is not specified

Processing Dates

AS Date 22 Mar 2022
TS Date 06 Jul 2022

Other details

Project Officers View