Project |
: Deposit work - Karunagappaliy Municipality - CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension and interconnection of distribution pipe line with 75 mm PVC CL3 pipe from Thondappuram Palam to Munduthara jn. in Division - 1 of Karunagappaliy Municipality. |
Project Code |
KLMDEPO072212383 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
: Deposit work - Karunagappaliy Municipality - CWSS to Oachira,
Karunagappally, Alappad and Clappana - Extension and interconnection of distribution pipe line
with 75 mm PVC CL3 pipe from Thondappuram Palam to Munduthara jn. in Division - 1 of
Karunagappaliy Municipality. |
Status |
Completed |
District |
Kollam |
Executing Office |
Chavara PH Sub Dn |
AS Amount (Rs) |
225000
|
AS Number |
RBI0812270211590 |
TS Amount (Rs) |
22500 |
TS Number |
9436/2022-2023 |
Total Bill Submitted (Rs) |
1 |
Total Bill Paid (Rs) |
1 |
Population Benefitted |
|
Capacity in MLD |
15.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
: Deposit work - Karunagappaliy Municipality - CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension and interconnection of distribution pipe line with 75 mm PVC CL3 pipe from Thondappuram Palam to Munduthara jn. in Division - 1 of Karunagappaliy Municipality. |
Oachira PH Sn |
|
2 |
: Deposit work - Karunagappaliy Municipality - CWSS to Oachira, Karunagappally, Alappad and Clappana - Extension and interconnection of distribution pipe line with 75 mm PVC CL3 pipe from Thondappuram Palam to Munduthara jn. in Division - 1 of Karunagappaliy Municipality. |
Chavara PH Sub Dn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
01 Feb 2023 |
Work Completed, Bill submitted on 23.11.2022 |
Oachira AE |
|
31 Jan 2023 |
Work Completed, Bill submitted on 23.11.2022 |
Oachira AE |
|
17 Oct 2022 |
Work completed |
Oachira AE |
|
14 Oct 2022 |
Work completed |
Oachira AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
20/08/2022 |
Scheduled date of Completion of the Project |
19 Sep 2022 |
Expected date of Completion |
Date is not specified |
Processing Dates
AS Date |
22 Mar 2022 |
TS Date |
06 Jul 2022 |