Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

STATE PLAN 2016-17-Making of unmanned security watch tower in Peppara and Aruvikkara

Project STATE PLAN 2016-17-Making of unmanned security watch tower in Peppara and Aruvikkara
Project Code TVMGOK07171905
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description Innovative Technologies and management practises-STATE PLAN-Making of unmanned security watch tower in Peppara and Aruvikkara
Status Completed
District Thiruvananthapuram
Executing Office Aruvikkara Sn 4
AS Amount (Rs) 2500000
AS Number G.O.(Rt) No. 892/2016/WRD
TS Amount (Rs) 2253000
TS Number 5367/2019-20
Total Bill Submitted (Rs) 1312722
Total Bill Paid (Rs) 0
Population Benefitted 862541
Capacity in MLD 86.00
Actual Project Completion Date 06 Nov 2021
Coverage Making of unmanned security watch tower in Peppara and Aruvikkara
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 STATE PLAN 2016-17-Making of unmanned security watch tower in Peppara and Aruvikkara Aruvikkara Sn 4
2 State -Plan 2016 -17 Unmanned security watch tower with CCTV camera and lighting at Aruvikkara and Peppara -Balance work at risk and cost Aruvikkara Sn 4

Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Dec 2021 Work Completed Aruvikkara Sn 4 AE
09 Nov 2021 Installation of CCTV camera at Aruvikkara and Peppara Dam premises progressing Aruvikkara Sn 4 AE
31 Oct 2021 Installation of CCTV camera at Aruvikkara and Peppara Dam premises progressing Aruvikkara Sn 4 AE
05 Oct 2021 Balance work started Aruvikkara Sn 4 AE
02 Oct 2021 Balance work tendered at the risk and cost of the original contractor and work awarded. Aruvikkara Sn 4 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 25/01/2020
Scheduled date of Completion of the Project 24 May 2020
Expected date of Completion 06/11/2021

Processing Dates

AS Date 16 Nov 2016
TS Date 13 Nov 2019

Other details

Project Officers View