State plan 2023-24 Optimization of production and transmission- Pipe line replacement- aug to BWSS- Relaying 80mm AC and 100mm AC pipe with 110mm PVC pipe at vadakara Municipality

Project State plan 2023-24 Optimization of production and transmission- Pipe line replacement- aug to BWSS- Relaying 80mm AC and 100mm AC pipe with 110mm PVC pipe at vadakara Municipality
Project Code CLTGOK072314523
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State plan 2023-24 Optimization of production and transmission- Pipe line replacement- aug to BWSS- Relaying 80mm AC and 100mm AC pipe with 110mm PVC pipe at vadakara Municipality
Status On-going
District Kozhikkode
Executing Office Vadakara WSP Sn
AS Amount (Rs) 3500000
AS Number KWA-JB/598/2023- AE 2- Part ( 1 )
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date 31 Mar 2024
Coverage Partial

Packages

No. Project Name Location View
1 State plan 2023-24 Optimization of production and transmission- Pipe line replacement- aug to BWSS- Relaying 80mm AC and 100mm AC pipe with 110mm PVC pipe at vadakara Municipality Vadakara WSP Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Feb 2024 Tender under scrutiny Vadakara PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion 30/04/2024

Processing Dates

AS Date 11 Jul 2023

Other details