Project | JJM-RWSS to Maloth-Balal Phase III |
---|---|
Project Code | KGDJJM022012466 |
Type | Main project |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | JJM-Maloth-Balal Phase III Survey and Investigation |
Status | Completed |
District | Kasaragod |
Executing Office | Kanhangad PH Sub Dn |
AS Amount (Rs) | 554600000 |
AS Number | GO(Rt)No.134/2022/WRD |
TS Amount (Rs) | 409000 |
TS Number | TS/2021-2022/2022/11050 |
Total Bill Submitted (Rs) | |
Total Bill Paid (Rs) | |
Population Benefitted | |
Capacity in MLD | |
Actual Project Completion Date | Date is not specified |
Coverage |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 Apr 2024 | Work has been completed | Kanhangad PH Sn AE | |
26 Mar 2024 | final design not obtained | Kanhangad PH Sn AE | |
14 Feb 2024 | final design not obtained | Kanhangad PH Sn AE | |
09 Nov 2023 | final design not obtained | Kanhangad PH Sn AE | |
01 Nov 2023 | final design not obtained | Kanhangad PH Sn AE |
Date of start of Project | 20/05/2022 |
---|---|
Scheduled date of Completion of the Project | 19 Jun 2022 |
Expected date of Completion | 30/06/2023 |
AS Date | 23 Feb 2022 |
---|---|
TS Date | 22 Mar 2022 |