Project | JAL JEEVAN MISSION -2021-22-PHASE III-Perumanna Panchayath - Providing FHTCs by extending existing line |
---|---|
Project Code | CLTJJM09219024P1 |
Type | Package |
Main Project | JAL JEEVAN MISSION -2021-22-PHASE III-Perumanna Panchayath - Providing FHTCs by extending existing line |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-02 |
Description | Providing FHTCs by extending existing line |
Status | Completed |
District | Kozhikkode |
Executing Office | Kozhikode Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 83400000 |
TS Number | TS/2021-2022/2021/16042 |
Technical specification | 90mm - 25000m PE pipe, 80mm GI pipe - 400m , providing 2800nos FHTC. |
Contractor | Zubair V (Mob: 9447131582) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 16/02/2022 |
---|---|
Scheduled date of Completion as per agreement | 15 Aug 2022 |
Expected date of Completion | 15/08/2022 |
TS Date | 23 Nov 2021 |
---|---|
Estimate Approval | 23 Nov 2021 |
Tender Closing | 17 Dec 2021 |
Price bid opening | 20 Dec 2021 |
Workorder Date | 16 Feb 2022 |
---|---|
NA | 07 Mar 2022 |
Kozhikode Project Dn AE5 |
Date: 31/03/2023 |
Work has been completed | 100% Completed
Work completed..
Kozhikode Project Dn AE5 |
Date: 30/03/2023 |
Work in progress | 94% Completed
90mm - 17000 m laid, 2100 FHTCs provided, Work in progress. .