Deposit work - Smart City Thiruvananthapuram Ltd - Reconstruction / Maintenance of Sewerage system of VIVEKANANDA NAGAR LANE (ROAD ID : 178), SREE CHITHRA ROAD (ROAD ID :179) near Tamil school Chalai due to work carried out by Smart City - Reg
Project |
Deposit work - Smart City Thiruvananthapuram Ltd - Reconstruction / Maintenance of Sewerage system of VIVEKANANDA NAGAR LANE (ROAD ID : 178), SREE CHITHRA ROAD (ROAD ID :179) near Tamil school Chalai due to work carried out by Smart City - Reg |
Project Code |
TVMSMARTCITY032210175 |
Type |
Main project |
Funding Agency |
SMARTCITY |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
Smart City |
Description |
Deposit work - Smart City Thiruvananthapuram Ltd - Reconstruction / Maintenance of Sewerage system of VIVEKANANDA NAGAR LANE (ROAD ID : 178), SREE CHITHRA ROAD (ROAD ID :179) near Tamil school Chalai due to work carried out by Smart City - Reg |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Kuriathy Sewerage Sn 2 |
AS Amount (Rs) |
3794800
|
AS Number |
SCTL/PRJ/210/2019/PMM/5325 |
TS Amount (Rs) |
3794800 |
TS Number |
23525/2021-2022 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
1000 |
Capacity in MLD |
0.05 |
Actual Project Completion Date |
16 Aug 2022 |
Coverage |
VIVEKANANDA NAGAR LANE (ROAD ID : 178) & SREE CHITHRA ROAD (ROAD ID :179) near Tamil school Chalai |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work - Smart City Thiruvananthapuram Ltd - Reconstruction / Maintenance of Sewerage system of VIVEKANANDA NAGAR LANE (ROAD ID : 178), SREE CHITHRA ROAD (ROAD ID :179) near Tamil school Chalai due to work carried out by Smart City - Reg |
Kuriathy Sewerage Sn 2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
10 Oct 2022 |
Work completed. |
Kuriathy Sewerage Sn2 AE |
|
03 Oct 2022 |
Work in progress |
Kuriathy Sewerage Sn2 AE |
|
26 Sep 2022 |
Work in progress |
Kuriathy Sewerage Sn2 AE |
|
19 Sep 2022 |
Work in progress |
Kuriathy Sewerage Sn2 AE |
|
12 Sep 2022 |
Pipe diversion completed |
Kuriathy Sewerage Sn2 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
17/04/2022 |
Scheduled date of Completion of the Project |
16 Aug 2022 |
Expected date of Completion |
15/10/2022 |
Processing Dates
AS Date |
21 Mar 2022 |
TS Date |
21 Mar 2022 |