Project | State Plan 2010-11 - WSS to Erumeli Panchayath |
---|---|
Project Code | KTMGOK09106017 |
Type | Main project |
Funding Agency | GOK |
Category | State plan |
Type of scheme | Water Supply |
Scheme | 2215-02-106-97 |
Description | Complete Water supply scheme including RWPH, 9MLD WTP , 6 Nos GLSR and 2 Nos OHSR by dividing the entire Panchayath in to 9 Zones. All production components including RWPH, WTP, Reservoirs , RWPM, CWGM, CWPM etc completed and the scheme commissioned on 20/11/2017. |
Status | On-going |
District | Kottayam |
Executing Office | Kottayam Project Dn |
AS Amount (Rs) | 530000000 |
AS Number | WS/2/2010-11 |
TS Amount (Rs) | 530000000 |
TS Number | 1/2011-12 |
Total Bill Submitted (Rs) | 476560000 |
Total Bill Paid (Rs) | 449100000 |
Population Benefitted | 43803 |
Capacity in MLD | 10.00 |
Actual Project Completion Date | 31 Mar 2022 |
Coverage | Entire erumely panchayath |
Implementation Schedule | Download |
Work Plan | Download |
No. | Project Name | Location | View |
---|---|---|---|
1 | WSS to Erumeli Panchayat in Kottayam District-Package 13-Pumps at TP MES college Jn. | Kottayam Project Dn | |
2 | WSS to Erumeli Panchayat in Kottayam District- Supplying, laying, testing, commissioning and maintenance of various size DI/PVC/GI pipes for laying distribution network from service reservoir at Karimkallumuzhy- Zone 3 (A) | Kottayam Project Dn |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Jul 2023 | The work delayed due to the pending permission of road cutting due to the unavailability of 1.3 Cr for RR charges for long time. 4km permission need to be obtained from KRFB in which the road is proposed for widening. Hence the pipeline can be laid only after new alignment fixing and formation of road. Contractor refused to lay the balance pipelines due to his pending payments of previous part bills. Bill submitted for Rs 23674697/-against cc5th and part bill as per direction for the completed works and is pending with HO for fund and payment. Also final bill of package 13 for amount Rs 8,11,756/- also pending for payment due to the lack of fund from HO | Kottayam Project Dn AE1 | |
22 Feb 2023 | The work delayed due to the pending permission of road cutting due to the unavailability of 1.3 Cr for RR charges . After remitting the same , PWD issued sanction for Pazhayidam- Chenapady road only saying the estimate taken in 2019 need to be revised which will be evaluated after completing the work on the permitted road ,. The work in the same is completed . Gap connection works and the commissioning of the laid pipeline works are in progress. 4km permission need to be obtained from KRFB in wich the road is proposed for widening. Hence the pipeline can be laid only after new alignment fixing and formation of road. Contractor refused to lay the balance pipelines due to his pending payments of previous part bills. Bill is under preparation for the completed works as per the directions. | Kottayam Project Dn AE1 | |
05 Aug 2022 | 41km/50km Completed. Work delayed due to pending road cutting sanction from PWD. RR charges was pending since 2019 for Rs 1.3 cr and the amount released on 26/05/2021 only and then the PWD objected sanction due to the revision in RR charges. Subsequent to the meeting held by the district collector on 29/09/2021 ,a meeting had with PWD EE and other field officers on 30.09.2021 in their office. Given permission to lay pipes in Manimala-Pazhayidam-Chenappady road from ch.4 to ch.15 . PWD will rework the road restoration estimate after the works in the road are completed as the rates are revised. PWD has rejected the request for laying pipes in Erumely-Mukkada road citing it is new BM & BC Road. Regarding Koratty-Orunkal Kadav road decision is kept pending to evaluate whether the amount is balance / excess required in the 1.3 Cr remitted after the allowed 10km laying completed. After the meeting by SE , PHC , the contractor restarted the work on 20/05/2022 and the laying of 400mm,300mm & 200mm DI along Pazhayidam - Chenappadi - Erumely is under progress. 9km out of 10km completed. Other three roads were applied along with JJM also. Meeting held at chamber of DC on 29/07/22 and PWD informed the permissions may be given after August 15 once the heavy rain stopped. | Kottayam Project Dn AE1 | |
13 Jun 2022 | 40km/50km Completed. Work delayed due to pending road cutting sanction from PWD. RR charges was pending since 2019 for Rs 1.3 cr and the amount released on 26/05/2021 only and then the PWD objected sanction due to the revision in RR charges. Susbsequent to the meeting held by the district collector on 29/09/2021 ,a meeting had with PWD EE and other field officers on 30.09.2021 in their office. Given permission to lay pipes in Manimala-Pazhayidam-Chenappady road from ch.4 to ch.15 after the end of ongoing rain. PWD will rework the road restoration estimate after the works in the road are completed as the rates are revised. PWD has rejected the request for laying pipes in Erumely-Mukkada road citing it is new BM & BC Road. Regarding Koratty-Orunkal Kadav road decision is kept pending to evaluate whether the amount is balance / excess required in the 1.3 Cr remitted after the allowed 10km laying completed. After the meeting by SE , PHC , the contractor restarted the work on 20/05/2022 and the laying of 400mm,300mm & 200mm DI along Pazhayidam - Chenappadi - Erumely is under progress. | Kottayam Project Dn AE1 | |
20 Dec 2021 | 37km/50km Completed. Work delayed due to pending road cutting sanction from PWD. RR charges was pending since 2019 for Rs 1.3 cr and the amount released on 26/05/2021 only and then the PWD objected sanction due to the revision in RR charges. Susbsequent to the meeting held by the district collector on 29/09/2021 ,a meeting had with PWD EE and other field officers on 30.09.2021 in their office. Given permission to lay pipes in Manimala-Pazhayidam-Chenappady road from ch.4 to ch.15 after the end of ongoing rain. PWD will rework the road restoration estimate after the works in the road are completed as the rates are revised. PWD has rejected the request for laying pipes in Erumely-Mukkada road citing it is new BM & BC Road. Regarding Koratty-Orunkal Kadav road decision is kept pending to evaluate whether the amount is balance / excess required in the 1.3 Cr remitted after the allowed 10km laying completed. But the Contracter given request letter to pre-close the work with his non willingness to continue further arguing the delay was not in his part and his last part bill also not yet released. | Kottayam Project Dn AE1 |
Review Date | Review Message | Review Attended By |
---|---|---|
21 Dec 2021 | Online review meeting conducted by MD,KWA on 21.12.21 for the work and attended. Directed to take decision at SE level and to report to HO regarding the request of the contractor to preclose the work. | EE |
18 Jun 2021 | Upload documents-correspondence with PWD for cutting permissions.Also urgently conduct a coordination committee meeting | EE.AE |
Date of start of Project | 11/05/2011 |
---|---|
Scheduled date of Completion of the Project | 31 Mar 2019 |
Expected date of Completion | 31/03/2023 |
AS Date | 22 Oct 2010 |
---|---|
TS Date | 03 Jun 2011 |
Project Officers | View |
---|