Jal Jeevan Mission (JJM) – Kannur District – Mokeri Grama Panchayath - WSS to Panniyannur, Panoor, Mokeri Phase .III – Construction of 9.3 LL OHSR at Valliyayi – Laying Pumping main and laying distribution system and providing FHTCs

Project Jal Jeevan Mission (JJM) – Kannur District – Mokeri Grama Panchayath - WSS to Panniyannur, Panoor, Mokeri Phase .III – Construction of 9.3 LL OHSR at Valliyayi – Laying Pumping main and laying distribution system and providing FHTCs
Project Code KNRJJM092114112P1
Type Package
Main Project Jal Jeevan Mission (JJM) – Kannur District – Mokeri Grama Panchayath - WSS to Panniyannur, Panoor, Mokeri Phase .III – Construction of 9.3 LL OHSR at Valliyayi – Laying Pumping main and laying distribution system and providing FHTCs
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description Construction of 9.30 LL OHSR, Laying distribution system and providing FHTCs
Status On-going
District Kannur
Executing Office Mattannur Project Dn
Agreement Number
Agreement Date
TS Amount (Rs) 206900000
TS Number 6213/2022-23
Technical specification Construction of 9.30 LL OHSR, Laying distribution system of 92 Km and 4363 Nos FHTCs
Contractor M/s K.K.Builders (Mob: 9496666556)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 10/03/2023
Scheduled date of Completion as per agreement 09 Dec 2023
Expected date of Completion 31/03/2025

Processing Dates

TS Date 21 Nov 2022
Estimate Approval 21 Nov 2022
NIT Approval 02 Feb 2023
Tender Closing 23 Jan 2023
Technichal Pre-Qualification 31 Dec 2022
Price bid opening 07 Feb 2023

Approval Dates

Workorder Date 10 Mar 2023
NA 24 Mar 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Mattannur Project Sn 2 AE
Date: 12/05/2025

Work in progress | 60% Completed

Earth excavation and Pipe laying is in progress at Pathippalam-Cheruvanchery Road. 75.30 km pipe laid completed out of 88.324 km distrbution. 1500 nos. HTC completed. Proposed OHSR (9.3LL) at valliyayi redesigned as raft foundation. Construction of 9.3LL OHSR at Valliyai is in progress, short Column up to plinth beam completed. LSGD Road restoration work is in progress, 6km completed.

Mattannur Project Sn 2 AE
Date: 03/05/2025

Work in progress | 59% Completed

Earth excavation and Pipe laying is in progress at Pathippalam-Cheruvanchery Road. 75.30 km pipe laid completed out of 88.324 km distrbution. 1500 nos. HTC completed. Proposed OHSR (9.3LL) at valliyayi redesigned as raft foundation. Construction of 9.3LL OHSR at Valliyai is in progress, short Column up to plinth beam completed. LSGD Road restoration work is in progress,5 km completed.