Project | Jal Jeevan Mission (JJM) – Kannur District – Mokeri Grama Panchayath - WSS to Panniyannur, Panoor, Mokeri Phase .III – Construction of 9.3 LL OHSR at Valliyayi – Laying Pumping main and laying distribution system and providing FHTCs |
---|---|
Project Code | KNRJJM092114112P1 |
Type | Package |
Main Project | Jal Jeevan Mission (JJM) – Kannur District – Mokeri Grama Panchayath - WSS to Panniyannur, Panoor, Mokeri Phase .III – Construction of 9.3 LL OHSR at Valliyayi – Laying Pumping main and laying distribution system and providing FHTCs |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Construction of 9.30 LL OHSR, Laying distribution system and providing FHTCs |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 206900000 |
TS Number | 6213/2022-23 |
Technical specification | Construction of 9.30 LL OHSR, Laying distribution system of 92 Km and 4363 Nos FHTCs |
Contractor | M/s K.K.Builders (Mob: 9496666556) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 10/03/2023 |
---|---|
Scheduled date of Completion as per agreement | 09 Dec 2023 |
Expected date of Completion | 31/03/2025 |
TS Date | 21 Nov 2022 |
---|---|
Estimate Approval | 21 Nov 2022 |
NIT Approval | 02 Feb 2023 |
Tender Closing | 23 Jan 2023 |
Technichal Pre-Qualification | 31 Dec 2022 |
Price bid opening | 07 Feb 2023 |
Workorder Date | 10 Mar 2023 |
---|---|
NA | 24 Mar 2023 |
Mattannur Project Sn 2 AE |
Date: 12/05/2025 |
Work in progress | 60% Completed
Earth excavation and Pipe laying is in progress at Pathippalam-Cheruvanchery Road. 75.30 km pipe laid completed out of 88.324 km distrbution. 1500 nos. HTC completed. Proposed OHSR (9.3LL) at valliyayi redesigned as raft foundation. Construction of 9.3LL OHSR at Valliyai is in progress, short Column up to plinth beam completed. LSGD Road restoration work is in progress, 6km completed.
Mattannur Project Sn 2 AE |
Date: 03/05/2025 |
Work in progress | 59% Completed
Earth excavation and Pipe laying is in progress at Pathippalam-Cheruvanchery Road. 75.30 km pipe laid completed out of 88.324 km distrbution. 1500 nos. HTC completed. Proposed OHSR (9.3LL) at valliyayi redesigned as raft foundation. Construction of 9.3LL OHSR at Valliyai is in progress, short Column up to plinth beam completed. LSGD Road restoration work is in progress,5 km completed.