DEPOSIT-Deposit work- Sasthamcotta Block Panchayath Project No 155/22 - Navadeepthi Drinking Water Project - 2021-22 --Extension of Pipe line ,Construction of Compound wall around the existing open well plot & Supply and errection of 5 HP Stand by open well submerssible pump set etc in Ward No.VI

Project DEPOSIT-Deposit work- Sasthamcotta Block Panchayath Project No 155/22 - Navadeepthi Drinking Water Project - 2021-22 --Extension of Pipe line ,Construction of Compound wall around the existing open well plot & Supply and errection of 5 HP Stand by open well submerssible pump set etc in Ward No.VI
Project Code KLMDEPO012415582
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Deposit work- Sasthamcotta Block Panchayath Project No 155/22 - Navadeepthi Drinking Water Project - 2021-22 --Extension of Pipe line ,Construction of Compound wall around the existing open well plot & Supply and errection of 5 HP Stand by open well submerssible pump set etc in Ward No.VI
Status On-going
District Kollam
Executing Office Sasthamcottah WS sub Dn
AS Amount (Rs) 3078200
AS Number S1/838/2023
TS Amount (Rs) 1066200
TS Number WRD/KWA-CE(SR)/EST_TS/466/2023_5_1_1 Dated: 05-02-2024
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 DEPOSIT-Deposit work- Sasthamcotta Block Panchayath Sasthamcottah WS Sn1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 May 2024 Agreement executed work not started Sasthamcotta WS Sn 1 - AE
14 May 2024 Agreement executed work not started Sasthamcotta WS Sn 1 - AE
10 May 2024 Agreement executed work not started Sasthamcotta WS Sn 1 - AE
07 May 2024 Agreement not executed Sasthamcotta WS Sn 1 - AE
03 May 2024 Agreement not executed Sasthamcotta WS Sn 1 - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 11 Jan 2024
TS Date 05 Feb 2024

Other details

Project Officers View