Jal Jeevan Mission-2020-22-Phase I- ARWSS to Pathanapuram and Piravanthoor-Providing Water Supply House Service Connections in existing distribution lines ,pipe line extension work and providing duel filter media in Pathanapuram Grama Panchayath

Project Jal Jeevan Mission-2020-22-Phase I- ARWSS to Pathanapuram and Piravanthoor-Providing Water Supply House Service Connections in existing distribution lines ,pipe line extension work and providing duel filter media in Pathanapuram Grama Panchayath
Project Code KLMJJM08203227
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Providing Water Supply House Service Connections
Status Completed
District Kollam
Executing Office Pathanapuram WS Sn
AS Amount (Rs) 328840000
AS Number G.O.(Rt)No.541/2020/WRD1
TS Amount (Rs) 53000000
TS Number TS/2020-2021/2020/16269
Total Bill Submitted (Rs) 39634687
Total Bill Paid (Rs) 39634687
Population Benefitted 12500
Capacity in MLD 6.00
Actual Project Completion Date 19 Jul 2022
Coverage Pathanapuram Panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission-2020-22-Phase I- ARWSS to Pathanapuram and Piravanthoor-Providing Water Supply House Service Connections in existing distribution lines ,pipe line extension work and providing duel filter media in Pathanapuram Grama Panchayath Pathanapuram WS Sn
2 JJM Pathanapuram GP for last mile connectivity - Minor line extension & last mile connectivity by using 50mm & 63mm PVC pipes Pathanapuram WS Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
16 Feb 2023 1916 FHTC completed Kottarakkara PH Dn EE
17 Sep 2022 1825/2500 connections provided in various wards. Kottarakkara PH Dn EE
31 May 2022 1725 FHTC completed and pipe laying works in progress Pathanapuram WS Sn - AE
24 May 2022 1725 FHTC completed and pipe laying works in progress Kottarakkara PH Dn EE
20 May 2022 1703 FHTC completed and pipe laying works in progress Pathanapuram WS Sn - AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 15/07/2021
Scheduled date of Completion of the Project 20 Feb 2023
Expected date of Completion 28/02/2023

Processing Dates

AS Date 21 Aug 2020
TS Date 08 Sep 2020

Other details

Project Officers View