Jal Jeevan Mission 2020-21- Providing Functional Household Tap Connections at Elamad Panchayath in Kollam District

Project Jal Jeevan Mission 2020-21- Providing Functional Household Tap Connections at Elamad Panchayath in Kollam District
Project Code KLMJJM08183129
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission 2020-21- Providing Functional Household Tap Connections at Elamad Panchayath in Kollam District
Status On-going
District Kollam
Executing Office Valakom PH Sub Dn
AS Amount (Rs) 183200000
AS Number GO RT NO.541/2020/WRD
TS Amount (Rs) 158000000
TS Number TS/2020-2021/2020/16314
Total Bill Submitted (Rs) 115220409
Total Bill Paid (Rs) 114135650
Population Benefitted 27132
Capacity in MLD 1.00
Actual Project Completion Date 31 Oct 2023
Coverage 27132 nos
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission 2020-21- Providing Functional Household Tap Connections at Elamad Panchayath in Kollam District Valakom PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 May 2024 107km pipe laying work and 5909 FHTC completed .Providing FHTC in ward of additional pipe laying work Valakom PH Sn AE
09 May 2024 107km pipe laying work and 5909 FHTC completed .Providing FHTC in ward of additional pipe laying work Valakom PH Sn AE
06 May 2024 107km pipe laying work and 5909 FHTC completed .Providing FHTC in ward of additional pipe laying work Valakom PH Sn AE
03 May 2024 107km pipe laying work and 5909 FHTC completed .Providing FHTC in ward of additional pipe laying work Valakom PH Sn AE
29 Apr 2024 107km pipe laying work and 5909 FHTC completed .Providing FHTC in ward of additional pipe laying work Valakom PH Sn AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 22/02/2021
Scheduled date of Completion of the Project 21 Feb 2022
Expected date of Completion 10/12/2022

Processing Dates

AS Date 25 Aug 2020
TS Date 04 Sep 2020

Other details

Project Officers View