- Home
- Jal Jeevan Mission 2020-21- Providing Fu...
Jal Jeevan Mission 2020-21- Providing Functional Household Tap Connections at Elamad Panchayath in Kollam District
Project |
Jal Jeevan Mission 2020-21- Providing Functional Household Tap Connections at Elamad Panchayath in Kollam District |
Project Code |
KLMJJM08183129 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission 2020-21- Providing Functional Household Tap Connections at Elamad Panchayath in Kollam District |
Status |
On-going |
District |
Kollam |
Executing Office |
Valakom PH Sub Dn |
AS Amount (Rs) |
183200000
|
AS Number |
GO RT NO.541/2020/WRD |
TS Amount (Rs) |
158000000 |
TS Number |
TS/2020-2021/2020/16314 |
Total Bill Submitted (Rs) |
115220409 |
Total Bill Paid (Rs) |
114135650 |
Population Benefitted |
27132 |
Capacity in MLD |
1.00 |
Actual Project Completion Date |
31 Oct 2023 |
Coverage |
27132 nos |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission 2020-21- Providing Functional Household Tap Connections at Elamad Panchayath in Kollam District |
Valakom PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 May 2024 |
107km pipe laying work and 5909 FHTC completed .Providing FHTC in ward of additional pipe laying work |
Valakom PH Sn AE |
|
09 May 2024 |
107km pipe laying work and 5909 FHTC completed .Providing FHTC in ward of additional pipe laying work |
Valakom PH Sn AE |
|
06 May 2024 |
107km pipe laying work and 5909 FHTC completed .Providing FHTC in ward of additional pipe laying work |
Valakom PH Sn AE |
|
03 May 2024 |
107km pipe laying work and 5909 FHTC completed .Providing FHTC in ward of additional pipe laying work |
Valakom PH Sn AE |
|
29 Apr 2024 |
107km pipe laying work and 5909 FHTC completed .Providing FHTC in ward of additional pipe laying work |
Valakom PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
22/02/2021 |
Scheduled date of Completion of the Project |
21 Feb 2022 |
Expected date of Completion |
10/12/2022 |
Processing Dates
AS Date |
25 Aug 2020 |
TS Date |
04 Sep 2020 |