- Home
- Deposit Work - Guruvayoor Municipality -...
Deposit Work - Guruvayoor Municipality - Engineering Wing 2020-21 Janakeeyasoothranna Project - Pipe line extension for Drinking Water Distribution in Ward 2.
Project |
Deposit Work - Guruvayoor Municipality - Engineering Wing 2020-21 Janakeeyasoothranna Project - Pipe line extension for Drinking Water Distribution in Ward 2. |
Project Code |
TCRDEPO06219411 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit Work - Guruvayoor Municipality - Engineering Wing 2020-21 Janakeeyasoothranna Project - Pipe line extension for Drinking Water Distribution in Ward 2. |
Status |
Completed |
District |
Thrissur |
Executing Office |
Guruvayur PH Sub Dn |
AS Amount (Rs) |
1000000
|
AS Number |
048530 |
TS Amount (Rs) |
1000000 |
TS Number |
14581/2021-2022 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
1 |
Capacity in MLD |
0.10 |
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit Work - Guruvayoor Municipality - Engineering Wing 2020-21 Janakeeyasoothranna Project - Pipe line extension for Drinking Water Distribution in Ward 2. |
Guruvayur PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Apr 2022 |
Wok completed. |
Guruvayur PH Sn AE |
|
21 Apr 2022 |
Wok completed. |
Guruvayur PH Sn AE |
|
20 Apr 2022 |
Wok completed. |
Guruvayur PH Sn AE |
|
19 Apr 2022 |
Wok completed. |
Guruvayur PH Sn AE |
|
18 Apr 2022 |
Wok completed. |
Guruvayur PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
03/12/2021 |
Scheduled date of Completion of the Project |
05 Mar 2022 |
Expected date of Completion |
05/03/2022 |
Processing Dates
AS Date |
14 Jun 2021 |
TS Date |
03 Dec 2021 |