Project | AMRUT 2015-16- THIRUVANANTHAPURAM SEWERAGE |
---|---|
Project Code | TVMAMRUT0316872 |
Type | Main project |
Funding Agency | AMRUT |
Category | AMRUT |
Type of scheme | Sewerage |
Scheme | AMRUT |
Description | Laying pumping main and supply of pumpset GO(Rt) No. 1329/2016/LSGD Dated 26/03/2016 of LSGD Amount-Rs.3.72Cr |
Status | Completed |
District | Thiruvananthapuram |
Executing Office | Pattoor Sewerage Dn |
AS Amount (Rs) | 37200000 |
AS Number | 1329/2016/LSGD dt 26/03/2016, 534/2017/LSGD dt 23.02.2017 revalidated 687/2021/LSGD dt 10/03/2021 |
TS Amount (Rs) | |
TS Number | |
Total Bill Submitted (Rs) | 34015734 |
Total Bill Paid (Rs) | 34015734 |
Population Benefitted | |
Capacity in MLD | |
Actual Project Completion Date | Date is not specified |
Coverage |
No. | Project Name | Location | View |
---|---|---|---|
1 | Paving inter locking tiles over trench portion inside BSF compound | Pattoor Sewerage Dn | |
2 | Supply of Pumpset for Kannamoola pump house | Pattoor Sewerage Dn | |
3 | Tss- Laying 900mm Dia DI Pumping main at Muttathara Sewage treatment plant and construction of new bridge with pile foundation and allied works | Pattoor Sewerage Dn |
Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
03 May 2021 | work completed | Pattoor Sewerage Dn | |
26 Apr 2021 | Compound wall construction started 94% completed | Pattoor Sewerage Dn | |
20 Apr 2021 | Work in progress | 94% Completed Repairing and fixing of gate is under progress, Tile side concrete under progress. | Pattoor Sewerage Dn | |
11 Apr 2021 | Maintenance of Gate in progress | Pattoor Sewerage Dn | |
31 Mar 2021 | Tile paving work completed, Tile side concrete work started. | Pattoor Sewerage Dn |
Date of start of Project | Date is not specified |
---|---|
Scheduled date of Completion of the Project | 23 Mar 2020 |
Expected date of Completion | 30/04/2021 |
AS Date | 23 Feb 2017 |
---|---|
TS Date | 22 Mar 2018 |
Project Officers | View |
---|