JJM- WSS to Alakkode and adjoining Panchayaths in Kannur District-Surveying distribution networks in Payyavoor,Eruvessi,Naduvil, Alakkode, Udayagiri, Peringome-Vayakkara and Cherupuzha Panchayaths

Project JJM- WSS to Alakkode and adjoining Panchayaths in Kannur District-Surveying distribution networks in Payyavoor,Eruvessi,Naduvil, Alakkode, Udayagiri, Peringome-Vayakkara and Cherupuzha Panchayaths
Project Code KNRJJM022210279P1
Type Package
Main Project JJM- WSS to Alakkode and adjoining Panchayaths in Kannur District-Surveying distribution networks in Payyavoor,Eruvessi,Naduvil, Alakkode, Udayagiri, Peringome-Vayakkara and Cherupuzha Panchayaths
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-01
Description This work is for Surveying distribution network for the scheme ,JJM- WSS to Alakkode and adjoining Panchayaths in Kannur District. Surveying for a total length of 1650.00km is proposed in this work in Seven Panchayaths viz. Payyavoor, Eruvessi, Naduvil, Alakkode, Udayagiri, Cherupuzha and Peringome-Vayakkara Panchayath. Total AS amount for this scheme is Rs.81589.51. Among these seven Panchayaths most of them are hilly area Panchayaths and so surveying in hill terrain is also proposed in this work.
Status Completed
District Kannur
Executing Office Payyannur Project Sn
Agreement Number
Agreement Date
TS Amount (Rs) 5300000
TS Number TS/2021-2022/2022/8718
Technical specification Surveying using Electronic Total Station with double prism in hilly terrain / normal terrain with heavy traffic -750 km Surveying using Electronic Total Station with double prism in normal terrain and normal traffic - 900 km

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 18/04/2022
Scheduled date of Completion as per agreement 17 Aug 2022
Expected date of Completion 17/08/2022

Processing Dates

TS Date 03 Mar 2022
Estimate Approval 03 Mar 2022
Tender Closing 10 Apr 2022
Price bid opening 12 Apr 2022

Approval Dates

Workorder Date 18 Apr 2022
NA 04 May 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Payyannur UIDSSMT AE 3
Date: 12/10/2022

Work has been completed | 100% Completed

Survey work completed.

Payyannur UIDSSMT AE 3
Date: 09/10/2022

Work has been completed | 100% Completed

Survey work completed.