Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

AMRUT 2.0 - FIFS - SUPPY,ERECTION AND COMMISSIONING OF CHLORINE LEAK ABSORPTION SYSTEM AT 36 MLD WTP, VELLAYAMBALAM MAIN SECTION , THIRUVANANTHAPURAM CORPORATION

Project AMRUT 2.0 - FIFS - SUPPY,ERECTION AND COMMISSIONING OF CHLORINE LEAK ABSORPTION SYSTEM AT 36 MLD WTP, VELLAYAMBALAM MAIN SECTION , THIRUVANANTHAPURAM CORPORATION
Project Code TVMAMRUT 2022314556
Type Main project
Funding Agency AMRUT 2
Category AMRUT 2
Type of scheme Water Supply
Scheme
Description AMRUT 2.0 - FIFS - SUPPY,ERECTION AND COMMISSIONING OF CHLORINE LEAK ABSORPTION SYSTEM AT 36 MLD WTP, VELLAYAMBALAM MAIN SECTION , THIRUVANANTHAPURAM CORPORATION
Status Short Closed
District Thiruvananthapuram
Executing Office Filter House Sn
AS Amount (Rs) 85000
AS Number G.O(RT)NO & 473/2023/LSGD
TS Amount (Rs) 85000
TS Number WRD/KWA-CE(SR)/EST_TS/4243/2022_12_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 AMRUT 2.0 - FIFS - SUPPY,ERECTION AND COMMISSIONING OF CHLORINE LEAK ABSORPTION SYSTEM AT 36 MLD WTP, VELLAYAMBALAM MAIN SECTION , THIRUVANANTHAPURAM CORPORATION Filter House Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
14 Feb 2024 Revised estimate submitted for sanction of Revised AS Head Quarter - AEE
10 Jan 2024 not started Thiruvananthapuram Ph Dn (S) EE
27 Dec 2023 Work not started Thiruvananthapuram Ph Dn (S) EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project Date is not specified
Expected date of Completion Date is not specified

Processing Dates

AS Date 23 Feb 2023
TS Date 08 May 2023

Other details

Project Officers View