Project | PACKAGE VII- CONSTRUCTION OF 11 LL CAPACITY OHSR AT AYITHARA COLONY , LAYING DISTRIBUTION SYSTEM AND PROVIDING FHTCs IN MANGATTIDAM GRAMA PANCHAYATH |
---|---|
Project Code | KNRJJM022213306P7 |
Type | Package |
Main Project | JJM-KANNUR DISTRICT- WSS TO TRIPPANGOTTUR & ADJOINING PANCHAYATHS |
Funding Agency | JJM |
Category | JJM |
Type of scheme | Water Supply |
Scheme | 4215-01-102-92-01 |
Description | Construction of 11 LL capacity OHSR at Ayithara colony ,supplying ,laying and commissioning distribution system , Providing 7706 Nos FHTCs |
Status | On-going |
District | Kannur |
Executing Office | Mattannur Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 593600000 |
TS Number | WRD/KWA-CE(NR)/EST_TS/7528/2022_26_1_1 |
Technical specification | Construction of 11 LL capacity OHSRat Ayithara colony ,supplying ,laying and commissioning distribution system , Providing 7706 Nos FHTCs |
Contractor | Baburaj P K (Mob: 9447152707) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 22/06/2023 |
---|---|
Scheduled date of Completion as per agreement | 21 Jun 2024 |
Expected date of Completion | 31/03/2025 |
TS Date | 02 Nov 2022 |
---|---|
Estimate Approval | 02 Nov 2022 |
NIT Approval | 02 Dec 2022 |
Tender Closing | 10 Apr 2023 |
Technichal Pre-Qualification | 22 Nov 2022 |
Price bid opening | 12 Apr 2023 |
Workorder Date | 26 May 2023 |
---|---|
NA | 12 Jun 2023 |
Mattannur Project Sn 2 AE |
Date: 12/05/2025 |
Work in progress | 95% Completed
EARTH EXCAVATION AND PIPE LAYING 99 % completed. Total Distribution is 206 km. 206 km pipe has supplied. out of this 204 km pipe laying completed. 6570 nos HTC completed. In this 1350 nos. FHTC charged. Construction of 11LL capacity OHSR at Ayithara completed. Plastering work also completed. inlet and outlet flow pipe and flange fixing work completed. 200mm wall casting(scour) pipe fixing also completed deck foot concreting completed. Inlet and outlet pipe entry and exit laying work completed. chamber of scour, Air valve completed . Reservoir compound wall work completed, plastering in progress. Ground floor PCC completed. 400 mm MS Connecting & fabrication work at Ayithara bridge completed.Distribution main line trial running, charging and scouring in up to Ayappanthode completed. Road restoration work also under progress.
Mattannur Project Sn 2 AE |
Date: 03/05/2025 |
Work in progress | 95% Completed
EARTH EXCAVATION AND PIPE LAYING IS IN PROGRESS. Total Distribution is 206 km. 206 km pipe has supplied. out of this 204 km pipe laying completed. 6570 nos HTC completed. In this 1350 nos. FHTC charged. Construction of 11LL capacity OHSR at Ayithara completed. Plastering work also completed. inlet and outlet flow pipe and flange fixing work completed. 200mm wall casting(scour) pipe fixing also completed deck foot concreting completed. Inlet and outlet pipe entry and exit laying work completed.chamber of scour, Air valve completed . Reservoir compound wall work completed, plastering in progress. Ground floor PCC completed. 400 mm MS Connecting & fabrication work at Ayithara bridge completed.Distribution main line trial running, charging and scouring in up to moonampeedika completed. Road restoration work also under progress.