Project | AMRUT 2.0 UWSS to Alappuzha Municipality -WSS to Alappuzha Municiplity providing distribution network in Alappuzha municipality |
---|---|
Project Code | ALPAMRUT112213107P3 |
Type | Package |
Main Project | Amrut 2.0-UWSS to Alappuzha Municipality |
Funding Agency | AMRUT 2 |
Category | AMRUT |
Type of scheme | Water Supply |
Scheme | |
Description | Supplying and laying of 33.50 Km pipe line in Alappuzha Municipality area |
Status | On-going |
District | Alappuzha |
Executing Office | Alappuzha Project Dn |
Agreement Number | |
Agreement Date | |
TS Amount (Rs) | 96930000 |
TS Number | WRD/KWA-CE(CR)/EST_TS/4673/2022_26_1_1 |
Technical specification | Supplying and laying of 33.50 Km pipe line in Alappuzha Municipality area 110mm PVC (8kg/cm2)-33500m |
Contractor | M/S ST MARYS ENGINEERING AND CONTRACTORS (Mob: 9447082519) |
Project Progress Status |
Project Progress Status |
No Status Updated |
Date of start of Package | 01/11/2023 |
---|---|
Scheduled date of Completion as per agreement | 25 Nov 2023 |
Expected date of Completion | Date is not specified |
TS Date | 02 Feb 2023 |
---|---|
Estimate Approval | 02 Feb 2023 |
NIT Approval | 12 Sep 2023 |
Tender Closing | 12 Jun 2023 |
Price bid opening | 13 Jun 2023 |
Workorder Date | 12 Sep 2023 |
---|---|
NA | 30 Sep 2023 |
Alappuzha Project Dn PM |
Date: 17/05/2024 |
Work in progress | 46% Completed
110 mm PVC laid out of 33500 meter PVC pipe to be laid 17491.5 meter laying has been completed. .
Alappuzha Project Dn PM |
Date: 16/05/2024 |
Work in progress | 46% Completed
110 mm PVC laid out of 33500 meter PVC pipe to be laid 17491.5 meter laying has been completed. .