DEPOSIT-Kochi Corporation-Laying 63mm PVC pipe in bylanes of Water way Avenue road & Bhagath Singh road,Puthan veedan lane bylane of St.James road,Lane no.10 Janatha road by using 63mm PVC(6kg/cm2) pipe in Div.No.52(new) part of 29(old) of Kochi Corporation-Pipeline Work

Project DEPOSIT-Kochi Corporation-Laying 63mm PVC pipe in bylanes of Water way Avenue road & Bhagath Singh road,Puthan veedan lane bylane of St.James road,Lane no.10 Janatha road by using 63mm PVC(6kg/cm2) pipe in Div.No.52(new) part of 29(old) of Kochi Corporation-Pipeline Work
Project Code EKMDEPO102213851P1
Type Package
Main Project DEPOSIT-Kochi Corporation-Laying 63mm PVC pipe in bylanes of Water way Avenue road & Bhagath Singh road,Puthan veedan lane bylane of St.James road,Lane no.10 Janatha road by using 63mm PVC(6kg/cm2) pipe in Div.No.52(new) part of 29(old) of Kochi Corporation-Pipeline Work
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-Kochi Corporation-Laying 63mm PVC pipe in bylanes of Water way Avenue road & Bhagath Singh road,Puthan veedan lane bylane of St.James road,Lane no.10 Janatha road by using 63mm PVC(6kg/cm2) pipe in Div.No.52(new) part of 29(old) of Kochi Corporation-Pipeline Work
Status Completed
District Ernakulam
Executing Office Vytilla Section 2
Agreement Number
Agreement Date
TS Amount (Rs) 590000
TS Number WRD/KWA-CE(CR)/EST_TS/11258/2022_26_1_1
Technical specification DEPOSIT-Kochi Corporation-Laying 63mm PVC pipe in bylanes of Water way Avenue road & Bhagath Singh road,Puthan veedan lane bylane of St.James road,Lane no.10 Janatha road by using 63mm PVC(6kg/cm2) pipe in Div.No.52(new) part of 29(old) of Kochi Corporation-Pipeline Work
Contractor K.B.Mukesh kumar (Mob: 9947426514)

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 27/01/2023
Scheduled date of Completion as per agreement 25 Feb 2023
Expected date of Completion 31/07/2023

Processing Dates

TS Date 06 Dec 2022
Estimate Approval 14 Oct 2022
NIT Approval 14 Oct 2022
Tender Closing 17 Dec 2022
Technichal Pre-Qualification 17 Dec 2022
Price bid opening 19 Dec 2023

Approval Dates

Workorder Date 31 Dec 2022
NA 27 Jan 2023

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Vytilla Section AE - 2
Date: 17/08/2023

Work has been completed | 100% Completed

Bill submitted to subdivision on 17.08.2023.

Vytilla Section AE - 2
Date: 01/08/2023

Work has been completed | 100% Completed

Work completed.Bill under preparation.