- Home
- Deposit work 2019-20 -RWSS to Pariyaram...
Deposit work 2019-20 -RWSS to Pariyaram - Pipe line extension and replacement for Kanjirappilly colony in Pariyaram Grama Panchayath
Project |
Deposit work 2019-20 -RWSS to Pariyaram - Pipe line extension and replacement for Kanjirappilly colony in Pariyaram Grama Panchayath |
Project Code |
TCRDEPO11219020 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work 2019-20 -RWSS to Pariyaram - Pipe line extension and replacement for Kanjirappilly colony in Pariyaram Grama Panchayath . |
Status |
Completed |
District |
Thrissur |
Executing Office |
Chalakkudy PH Sn II |
AS Amount (Rs) |
110000
|
AS Number |
A1-4611/2021 |
TS Amount (Rs) |
110000 |
TS Number |
TS/2021-2022/2020/19532 |
Total Bill Submitted (Rs) |
99274 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
100 |
Capacity in MLD |
1.08 |
Actual Project Completion Date |
24 Feb 2022 |
Coverage |
Kanjirappilly colony |
Packages
No. |
Project Name |
Location |
View |
1 |
Deposit work 2019-20 -RWSS to Pariyaram - Pipe line extension and replacement for Kanjirappilly colony in Pariyaram Grama Panchayath |
Chalakkudy PH Sn II |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Jul 2022 |
CC 1st and final bill submitted to division on 18.03.2022 |
Chalakudy AEE |
|
14 Mar 2022 |
cc 1 st and final bill submitted to subdivision on 11-3-2022 |
Chalakudy AE 2 |
|
02 Mar 2022 |
work completed |
Chalakudy AE 2 |
|
28 Feb 2022 |
work completed |
Chalakudy AE 2 |
|
24 Feb 2022 |
work completed |
Chalakudy AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
21/02/2022 |
Scheduled date of Completion of the Project |
13 Mar 2022 |
Expected date of Completion |
24/02/2022 |
Processing Dates
AS Date |
12 Nov 2021 |
TS Date |
29 Jan 2022 |