Deposit work Karakulam Grama Panchayath (Urban Agglomoration Project-Augumentation UWSS to Karakulam-Renovation of water Treatment Plant and Landscape,Painting,boundary fencing and other Maintenance works in plant,CWPH and RWPH at Kummy

Project Deposit work Karakulam Grama Panchayath (Urban Agglomoration Project-Augumentation UWSS to Karakulam-Renovation of water Treatment Plant and Landscape,Painting,boundary fencing and other Maintenance works in plant,CWPH and RWPH at Kummy
Project Code TVMDEPO01229886
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description Deposit work Karakulam Grama Panchayath (Urban Agglomoration Project-Augumentation UWSS to Karakulam-Renovation of water Treatment Plant and Landscape,Painting,boundary fencing and other Maintenance works in plant,CWPH and RWPH at Kummy
Status Completed
District Thiruvananthapuram
Executing Office Nedumangad WW Sn
AS Amount (Rs) 7500000
AS Number 111-278/2021
TS Amount (Rs) 7500000
TS Number 23316/2021-2022
Total Bill Submitted (Rs) 6858107
Total Bill Paid (Rs) 6105107
Population Benefitted 30000
Capacity in MLD 5.00
Actual Project Completion Date Date is not specified
Coverage Deposit work Karakulam Grama Panchayath (Urban Agglomoration Project-Augumentation UWSS to Karakulam-Renovation of water Treatment Plant and Landscape,Painting,boundary fencing and other Maintenance works in plant,CWPH and RWPH at Kummy
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Deposit work Karakulam Grama Panchayath (Urban Agglomoration Project-Augumentation UWSS to Karakulam-Renovation of water Treatment Plant and Landscape,Painting,boundary fencing and other Maintenance works in plant,CWPH and RWPH at Kummy Nedumangad WW Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
04 Feb 2023 work going on Aruvikkara HW Dn EE
31 Jan 2023 work going on Aruvikkara HW Dn EE
27 Jan 2023 work going on Nedumangad AE
25 Jan 2023 work going on Aruvikkara HW Dn EE
21 Jan 2023 work going on Aruvikkara HW Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 12/04/2022
Scheduled date of Completion of the Project 12 Aug 2022
Expected date of Completion 30/09/2022

Processing Dates

AS Date 24 Jan 2022
TS Date 19 Mar 2022