Annual Plan 2018 - 19 - Augmentation of Nemmara, Ayiloor and Melarcode WSS - Phase III - in Chittur and Alathur Taluk - Supply and laying distribution system using DI, GI, PVC pipes of size 200 mm DI K9 to 90mm PVC.
Project |
Annual Plan 2018 - 19 - Augmentation of Nemmara, Ayiloor and Melarcode WSS - Phase III - in Chittur and Alathur Taluk - Supply and laying distribution system using DI, GI, PVC pipes of size 200 mm DI K9 to 90mm PVC. |
Project Code |
PKDGOK0818986 |
Type |
Main project |
Funding Agency |
GOK |
Category |
State plan |
Type of scheme |
Water Supply |
Scheme |
2215-02-106-97 |
Description |
Annual Plan 2018 - 19 - Augmentation of Nemmara, Ayiloor and Melarcode WSS - Phase III - in Chittur and Alathur Taluk - Supply and laying distribution system using DI, GI, PVC pipes of size 200 mm DI K9 to 90mm PVC. |
Status |
Completed |
District |
Palakkad |
Executing Office |
Nenmara Sn |
AS Amount (Rs) |
146000000
|
AS Number |
GO(Rt).No.571/2018/WRD |
TS Amount (Rs) |
142900000 |
TS Number |
TS/2018-19/2018/10239 |
Total Bill Submitted (Rs) |
98962000 |
Total Bill Paid (Rs) |
63583000 |
Population Benefitted |
131619 |
Capacity in MLD |
12.50 |
Actual Project Completion Date |
22 Dec 2021 |
Coverage |
112km distribution in Nenmara & Ayilur Panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Annual Plan 2018 - 19 - Augmentation of Nemmara, Ayiloor and Melarcode WSS - Phase III - in Chittur and Alathur Taluk - Supply and laying distribution system using DI, GI, PVC pipes of size 200 mm DI K9 to 90mm PVC. |
Nenmara Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
20 Dec 2022 |
Work completed and CC 5th and final bill submitted on 09/12/22 |
Palakkad PH Dn EE |
|
23 Aug 2022 |
Work ccompleted .Bill under preparation |
Palakkad PH Dn EE |
|
14 Feb 2022 |
Work ongoing. 90% Completed |
Palakkad PH Dn EE |
|
04 Oct 2021 |
Road Restoration fund Rs 10000705/- Remitted to PWD on 29/9/2021 |
Palakkad PH Dn EE |
|
09 Aug 2021 |
As amount 14.6 crore, APAC-9.436 crore, road restoration remitted -1.79 crore , Total length of pipe line 112km , so far laid 90km ,Balance to be laid 22km for which road restoration required 1.07 crore, its estimate submitted |
Palakkad PH Dn EE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
25/05/2019 |
Scheduled date of Completion of the Project |
25 Feb 2020 |
Expected date of Completion |
28/02/2022 |
Processing Dates
AS Date |
01 Aug 2018 |
TS Date |
27 Sep 2018 |