Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

DEPOSITE WORK-Karakulam Grama Panchayath -Pipe line extension to Greenvalley lane in Mudisasthamcode,Puravoorkonam lane in Vazhayila ward,Chekkakonam and Plathara and Joseph lane-Mudippura road in Kachani ward.

Project DEPOSITE WORK-Karakulam Grama Panchayath -Pipe line extension to Greenvalley lane in Mudisasthamcode,Puravoorkonam lane in Vazhayila ward,Chekkakonam and Plathara and Joseph lane-Mudippura road in Kachani ward.
Project Code TVMDEPO01229265
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSITE WORK-Karakulam Grama Panchayath -Pipe line extension to Greenvalley lane in Mudisasthamcode,Puravoorkonam lane in Vazhayila ward,Chekkakonam and Plathara and Joseph lane-Mudippura road in Kachani ward.
Status Completed
District Thiruvananthapuram
Executing Office Nedumangad WW Sn
AS Amount (Rs) 989000
AS Number NoB1/226/16
TS Amount (Rs) 989000
TS Number 19401/2021-2022,19398/2021-2022,19405/2021-2022,19406/2021-2022
Total Bill Submitted (Rs) 868218
Total Bill Paid (Rs) 654747
Population Benefitted 200
Capacity in MLD 0.15
Actual Project Completion Date Date is not specified
Coverage

Packages

No. Project Name Location View
1 DEPOSITE WORK-Karakulam Grama Panchayath -Pipe line extension to Greenvalley lane in Mudisasthamcode,Puravoorkonam lane in Vazhayila ward,Chekkakonam and Plathara and Joseph lane-Mudippura road in Kachani ward. Nedumangad WW Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Dec 2022 work completed Nedumangad AE
14 Oct 2022 work completed Nedumangad AE
31 Aug 2022 work completed Nedumangad AE
27 Jul 2022 work completed Nedumangad AE
24 Jul 2022 work completed Nedumangad AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 25/02/2022
Scheduled date of Completion of the Project 24 Jun 2022
Expected date of Completion 24/06/2022

Processing Dates

AS Date 27 Jan 2022
TS Date 04 Feb 2022

Other details

Project Officers View