MPLADS - 2022-23-Honarable MP Adv. A.M. Ariff - Supply, Erection, Testing and Commissioning of Skid Mounted 500 LPH output Capacity R O Plant capable to remove TDS up to 2000 PPM with all accessories in Govt. Womens Polytechnic College, Kayamkulam.

Project MPLADS - 2022-23-Honarable MP Adv. A.M. Ariff - Supply, Erection, Testing and Commissioning of Skid Mounted 500 LPH output Capacity R O Plant capable to remove TDS up to 2000 PPM with all accessories in Govt. Womens Polytechnic College, Kayamkulam.
Project Code ALPDC-LAC/ADS/SDF/KSCADC112213396
Type Main project
Funding Agency DC-LAC/ADS/SDF/KSCADC
Category MPLADS
Type of scheme Water Supply
Scheme DC-LAC/ADS/SDF/KSCADC
Description Supply, Erection, Testing and Commissioning of Skid Mounted 500 LPH output Capacity R O Plant capable to remove TDS up to 2000 PPM with all accessories in Govt. Womens Polytechnic College, Kayamkulam.
Status Completed
District Alappuzha
Executing Office Harippad WS Sub Dn
AS Amount (Rs) 295000
AS Number 926/2022/DPO/ALP/MPLADS/AMS(03)
TS Amount (Rs) 295000
TS Number WRD/KWA-CE(CR)/EST_TS/5234/2022_5_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted
Capacity in MLD
Actual Project Completion Date 06 Mar 2023
Coverage

Packages

No. Project Name Location View
1 MPLADS - 2022-23-Honarable MP Adv. A.M. Ariff - Supply, Erection, Testing and Commissioning of Skid Mounted 500 LPH output Capacity R O Plant capable to remove TDS up to 2000 PPM with all accessories in Govt. Womens Polytechnic College, Kayamkulam. Kayamkulam PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
07 Mar 2023 COMPLETED Kayamkulam AE
06 Mar 2023 started Kayamkulam AE
03 Mar 2023 started Kayamkulam AE
01 Mar 2023 started Kayamkulam AE
21 Feb 2023 started Kayamkulam AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 20/01/2023
Scheduled date of Completion of the Project 20 Feb 2023
Expected date of Completion 20/02/2023

Processing Dates

AS Date 05 Nov 2022
TS Date 24 Nov 2022

Other details

Project Officers View