Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

State Plan 2021-22 : TSS-Increasing capacity of 150mm SW pipe to 200mm SW pipe andconstructing RCC manholes at manacaud valiyapalli ,Thampuran nagar ,Avittom thirunaal welfareAssociation, CRW-77 TO 82 and KRWA-144 TO 155 under sewerage section 1,Kuriathy

Project State Plan 2021-22 : TSS-Increasing capacity of 150mm SW pipe to 200mm SW pipe andconstructing RCC manholes at manacaud valiyapalli ,Thampuran nagar ,Avittom thirunaal welfareAssociation, CRW-77 TO 82 and KRWA-144 TO 155 under sewerage section 1,Kuriathy
Project Code TVMGOK10218310
Type Main project
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State Plan 2021-22 : TSS-Increasing capacity of 150mm SW pipe to 200mm SW pipe and constructing RCC manholes at Manacaud valiyapalli ,Thampuran nagar ,Avittom Thirunaal welfare Association, CRW-77 TO 82 and KRWA-144 TO 155 under sewerage section 1,Kuriathy
Status Completed
District Thiruvananthapuram
Executing Office Kuriathy Sewerage Sn 1
AS Amount (Rs) 4830000
AS Number KWA/JB/PIU1/12/2021
TS Amount (Rs) 4760000
TS Number 12732/2021-2022
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 1000
Capacity in MLD 0.20
Actual Project Completion Date 01 Jun 2022
Coverage Various places in Kuriathy ward
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 State Plan 2021-22 : TSS-Increasing capacity of 150mm SW pipe to 200mm SW pipe andconstructing RCC manholes at manacaud valiyapalli ,Thampuran nagar ,Avittom thirunaal welfareAssociation, CRW-77 TO 82 and KRWA-144 TO 155 under sewerage section 1, Kuriathy Kuriathy Sewerage Sn 1

Overall Project Status

Status Date Overall Project Status Project Officer Contact
03 Jun 2022 Work completed. Kuriathy Sewerage Sn1 AE
31 May 2022 99%: Work completed in Thampuran Nagar, KRWA, CRWA & Avittom Thirunal Welfare Association and NSS Karayogam. For, Valiyapalli lane, Pipe laying and MH work completed, restoration concrete only pending. Delayed due to rain. Restoration concrete work started from 30/5/2022 due to good weather, about 25 M completed, work in progress. Kuriathy Sewerage Sn1 AE
30 May 2022 98%: Work completed in Thampuran Nagar, KRWA, CRWA & Avittom Thirunal Welfare Association and NSS Karayogam. For, Valiyapalli lane, Pipe laying and MH work completed, restoration concrete only pending. Delayed due to rain. Planned on 31/05/2022. Earth levelling for concrete in progress. Kuriathy Sewerage Sn1 AE
25 May 2022 98%: Work completed in Thampuran Nagar, KRWA, CRWA & Avittom Thirunal Welfare Association and NSS Karayogam. For, Valiyapalli lane, Pipe laying and MH work completed, restoration concrete only pending. Delayed due to rain. Planned on 27/05/2022. Earth levelling for concrete in progress. Kuriathy Sewerage Sn1 AE
24 May 2022 97%: Work completed in Thampuran Nagar, KRWA, CRWA & Avittom Thirunal Welfare Association and NSS Karayogam. For, Valiyapalli lane, Pipe laying and MH work completed, restoration concrete only pending. Delayed due to rain. Kuriathy Sewerage Sn1 AE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 02/12/2021
Scheduled date of Completion of the Project 01 Jun 2022
Expected date of Completion 01/06/2022

Processing Dates

AS Date 25 Oct 2021
TS Date 09 Nov 2021

Other details

Project Officers View