DEPOSIT-District panchayat 2021-2022-Supply , Erection,Testing and Commissioning of Skid Mounted 250 LPH Output Capacity R O Plant Capable to remove TDS up to 2000 PPM with all accessories in HS Charamangalam in Kanjikuzhy Panchayat

Project DEPOSIT-District panchayat 2021-2022-Supply , Erection,Testing and Commissioning of Skid Mounted 250 LPH Output Capacity R O Plant Capable to remove TDS up to 2000 PPM with all accessories in HS Charamangalam in Kanjikuzhy Panchayat
Project Code ALPDEPO022314258
Type Main project
Funding Agency DEPO
Category Deposit Work
Type of scheme Water Supply
Scheme DEPO
Description DEPOSIT-District panchayat 2021-2022-Supply , Erection,Testing and Commissioning of Skid Mounted 250 LPH Output Capacity R O Plant Capable to remove TDS up to 2000 PPM with all accessories in HS Charamangalam in Kanjikuzhy Panchayat
Status Completed
District Alappuzha
Executing Office Cherthala PH Sn
AS Amount (Rs) 273000
AS Number HL-5359(1)/22
TS Amount (Rs) 273000
TS Number 16587/2022-2023
Total Bill Submitted (Rs) 0
Total Bill Paid (Rs) 0
Population Benefitted 500
Capacity in MLD 107.00
Actual Project Completion Date 23 Nov 2023
Coverage Govt. High School, Charamangalam
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 DEPOSIT-District panchayat 2021-2022-Supply , Erection,Testing and Commissioning of Skid Mounted 250 LPH Output Capacity R O Plant Capable to remove TDS up to 2000 PPM with all accessories in HS Charamangalam in Kanjikuzhy Panchayat Cherthala PH Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Dec 2023 E bill under scrutiny in Sub Division Cherthala PH SUb Dn
16 Dec 2023 E bill received in Sub Division Cherthala PH SUb Dn
23 Nov 2023 Work completed Cherthala PH SUb Dn
16 Nov 2023 Work under progress Cherthala PH SUb Dn
10 Nov 2023 Materials supplied Cherthala PH SUb Dn

No project review have been added to this project

Duration & Sanction dates

Date of start of Project Date is not specified
Scheduled date of Completion of the Project 23 Aug 2023
Expected date of Completion 30/11/2023

Processing Dates

AS Date 09 Feb 2023
TS Date 17 Mar 2023

Other details

Project Officers View