Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission(JJM)- Alappuzha District- Providing Functional Household Tap Connection (FHTC) in Muhamma Grama Panchayat and Allied Works

Project Jal Jeevan Mission(JJM)- Alappuzha District- Providing Functional Household Tap Connection (FHTC) in Muhamma Grama Panchayat and Allied Works
Project Code ALPJJM08205783P2
Type Package
Main Project Jaljeevan- Providing Household retrofittable/extentable water service connections in Muhamma Panchayath in Alappuzha District
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission(JJM)- Alappuzha District- Providing Functional Household Tap Connection (FHTC) in Muhamma Grama Panchayat and Allied Works
Status On-going
District Alappuzha
Executing Office Alappuzha WSP Sn
Agreement Number
Agreement Date
TS Amount (Rs) 63520000
TS Number ts/2020-2021/2020/16414
Technical specification Providing Functional Household Tap Connection (FHTC) in Muhamma Grama Panchayat and Allied Works

No project review have been added to this project

Reported Issues

Issue date Solved On Action Taken On Category Description Comments Issue Status
25 Sep 2021 Pending Pending Natural Calamities Related High Water Table No comments available. Pending
25 Sep 2021 Pending Pending Natural Calamities Related Frequent Lockdown due to Covid-19 No comments available. Pending

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 24/12/2020
Scheduled date of Completion as per agreement 31 May 2021
Expected date of Completion 30/11/2021

Processing Dates

TS Date 27 Aug 2020
Estimate Approval 27 Aug 2020
NIT Approval 09 Sep 2020
Tender Closing 30 Oct 2020
Technichal Pre-Qualification 02 Nov 2020
Price bid opening 30 Nov 2020

Approval Dates

Workorder Date 18 Dec 2020
NA 18 Dec 2020

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Alappuzha WSP Sn AE
Date: 24/01/2024

Work in progress | 75% Completed

3700 Nos FHTC Completed.

Alappuzha WSP Sn AE
Date: 01/01/2024

Work in progress | 74% Completed

Few New Connections to be given to complete the project.