KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package I
| Project |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package I |
| Project Code |
ALPKIIFB0919495P1 |
| Type |
Package |
| Main Project |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality
|
| Funding Agency |
KIIFB |
| Category |
KIIFB WATER SUPPLY SCHEME |
| Type of scheme |
Water Supply |
| Scheme |
KIIFB |
| Description |
Construction of 35 MLD Water Treatment Plant with parallel plate clarifier, Renovation to existing Intake well cum Pump house -10 m Dia and Intake arrangements, Supply and laying Raw water Pumping main -700 DI K9 - 3050m Construction of OHSR 14.00 LL Capacity and 14.60 LL Sump cum Pump house at WTP, , Supply and erection testing and commissioning of raw water pump sets 270 HP VT 3 nos and Supply and erection testing commissioning of clear water pump set 75 HP CF-5 numbers, 25 HP CF-2 numbers, at clear water Sump, Substation and Transformer at intake pump house Kolamukkam, Design Supply, Erection, Testing and Commissioning of one No.750 KVA, 11 KV/3.30 K V Indoor Transformers and connected works at Raw Water Pump House, Kolamukkam, Substation and Transformer at WTP, Nikarumpuram Design, Supply, Erection, Testing and Commissioning of One Nos.400 KVA, 11 KV/433 V Indoor Transformers and connected works at WTP, Road Restoration works and allied works.
|
| Status |
On-going |
| District |
Alappuzha |
| Executing Office |
KIIFB Projects (ALP) |
| Agreement Number |
|
| Agreement Date |
|
| TS Amount (Rs) |
388811875 |
| TS Number |
TS/2019-2020/2020/569 |
| Technical specification |
35 MLD Water Treatment Plant with parallel plate clarifier
Raw water Pumping main -700 DI K9 - 3050m
CWPM/CWGM - 400mm DI K9 pipe-380m, 350 mm DI K9 pipe-110m, 160 mm PVC 10 Kg pipe-1560m, 110 mm PVC 10 Kg pipe-2180m, 90 mm PVC 10 Kg pipe-740m, 75 mm PVC 10 Kg pipe-170m
Construction of OHSR 14.00 LL Capacity and 14.60 LL Sump cum Pump house at WTP
Raw water pump sets - 270 HP VT 3 nos
Clear water pump set - 75 HP CF-5 numbers, 25 HP CF-2 numbers. |
| Contractor |
M/s Chicago constructions International pvt ltd (Mob: 9447770536) |
No project review have been added to this project
Reported Issues
| Issue date |
Solved On |
Action Taken On |
Category |
Description |
Comments |
Issue Status |
| 30 Nov 2021 |
Pending |
Pending |
Road Cut Related Risk |
PWD permission not obtained |
No comments available. |
Pending |
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
19/10/2020 |
| Scheduled date of Completion as per agreement |
25 Aug 2022 |
| Expected date of Completion |
31/03/2023 |
Processing Dates
| TS Date |
11 Jan 2020 |
| Estimate Approval |
08 Jan 2020 |
| NIT Approval |
28 Jan 2020 |
| Tender Closing |
24 Feb 2020 |
| Technichal Pre-Qualification |
04 Mar 2020 |
| Price bid opening |
19 May 2020 |
Approval Dates
| Workorder Date |
30 Jun 2020 |
| NA |
25 Aug 2020 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| Alappuzha KIIFB - AE 1 |
| Date: 30/04/2026 |
Work has been completed | 100% Completed
Construction of 35MLD WTP and allied works completed. The trial running and commissioning will be done only after completion of laying pumping main from WTP to OHSR. The work for dedicated power connection to WTP and Intake well is completed . After getting HT connection, Raw water pumping main charged on 13.11.2024..
| Alappuzha KIIFB - AE 1 |
| Date: 27/04/2026 |
Work has been completed | 100% Completed
Construction of 35MLD WTP and allied works completed. The trial running and commissioning will be done only after completion of laying pumping main from WTP to OHSR. The work for dedicated power connection to WTP and Intake well is completed . After getting HT connection, Raw water pumping main charged on 13.11.2024..