KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package I
| Project |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package I |
| Project Code |
ALPKIIFB0919495P1 |
| Type |
Package |
| Main Project |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality
|
| Funding Agency |
KIIFB |
| Category |
KIIFB WATER SUPPLY SCHEME |
Type of scheme |
Water Supply |
| Description |
Construction of 35 MLD Water Treatment Plant with parallel plate clarifier, Renovation to existing Intake well cum Pump house -10 m Dia and Intake arrangements, Supply and laying Raw water Pumping main -700 DI K9 - 3050m Construction of OHSR 14.00 LL Capacity and 14.60 LL Sump cum Pump house at WTP, , Supply and erection testing and commissioning of raw water pump sets 270 HP VT 3 nos and Supply and erection testing commissioning of clear water pump set 75 HP CF-5 numbers, 25 HP CF-2 numbers, at clear water Sump, Substation and Transformer at intake pump house Kolamukkam, Design Supply, Erection, Testing and Commissioning of one No.750 KVA, 11 KV/3.30 K V Indoor Transformers and connected works at Raw Water Pump House, Kolamukkam, Substation and Transformer at WTP, Nikarumpuram Design, Supply, Erection, Testing and Commissioning of One Nos.400 KVA, 11 KV/433 V Indoor Transformers and connected works at WTP, Road Restoration works and allied works.
|
| Status |
On-going |
| District |
Alappuzha |
| Executing Office |
KIIFB Projects (ALP) |
| TS Amount (Rs) |
388811875 |
| TS Number |
TS/2019-2020/2020/569 |
| Technical specification |
35 MLD Water Treatment Plant with parallel plate clarifier
Raw water Pumping main -700 DI K9 - 3050m
CWPM/CWGM - 400mm DI K9 pipe-380m, 350 mm DI K9 pipe-110m, 160 mm PVC 10 Kg pipe-1560m, 110 mm PVC 10 Kg pipe-2180m, 90 mm PVC 10 Kg pipe-740m, 75 mm PVC 10 Kg pipe-170m
Construction of OHSR 14.00 LL Capacity and 14.60 LL Sump cum Pump house at WTP
Raw water pump sets - 270 HP VT 3 nos
Clear water pump set - 75 HP CF-5 numbers, 25 HP CF-2 numbers. |
No project review have been added to this project
|
Project Progress Status
|
Project Progress Status
|
Duration & Sanction dates
| Date of start of Package |
19/10/2020 |
| Scheduled date of Completion as per agreement |
25 Aug 2022 |
| Expected date of Completion |
25/08/2022 |
Processing Dates
| AS Date |
07 Sep 2019 |
| TS Date |
11 Jan 2020 |
| Estimate Approval |
08 Jan 2020 |
| NIT Approval |
28 Jan 2020 |
| Tender Closing |
24 Feb 2020 |
Approval Dates
| Workorder Date |
30 Jun 2020 |
| Agreement Date |
26 Aug 2020 |
Other details
| Project Schedule |
View |
| Project Components |
View |
| Project Officers |
View |
| AE1 KIIFB ALP |
| Date: 07/06/2021 |
Work in progress | 15% Completed
Raw water pumping main- 700mm DI K9 pipe and 110/90/75mm PVC pipe distribution network laying work in progress. 35MLD WTP- Sump cum filter house RCC work of wall and column in progress . Plate settler clarifier- H launder RCC work in progress..
| AE1 KIIFB ALP |
| Date: 06/06/2021 |
Work in progress | 15% Completed
Raw water pumping main- 700mm DI K9 pipe and 110/90/75mm PVC pipe distribution network laying work in progress. 35MLD WTP- Sump cum filter house RCC work of wall and column in progress . Plate settler clarifier- H launder RCC work in progress..