Jal Jeevan Mission-Kasaragod District-Panathady Panchayat-WSS to Panathady and Kallar Phase II
Project |
Jal Jeevan Mission-Kasaragod District-Panathady Panchayat-WSS to Panathady and Kallar Phase II |
Project Code |
KGDJJM08203011 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Laying distribution line and providing FHTCs in Pananthady Panchayath.
Distribution network - 50 pvc 12.5 kg - 3500 m, 63 pvc 12.5 kg - 500 m, 90 pvc 12.5 kg - 500 m, 110 pvc 12.5 kg - 300m, 140 pvc 12.5 kg - 360 m, 50 pvc 10 kg - 6500 m, 63 pvc 10kg - 1500 m, 90 pvc 10kg - 1500 m, 110 pvc 10 kg - 5700 m, 100 mm GI - 100 m, 20 pvc 12.5 kg - 53000 m,
FHTCs - 1200 nos. |
Status |
Completed |
District |
Kasaragod |
Executing Office |
Project Division Kannur ( KGD) |
AS Amount (Rs) |
55000000
|
AS Number |
GO.(Rt)No.541/2020/WRD |
TS Amount (Rs) |
52800000 |
TS Number |
TS/2020-2021/2020/17018 |
Total Bill Submitted (Rs) |
26194819 |
Total Bill Paid (Rs) |
26194819 |
Population Benefitted |
6000 |
Capacity in MLD |
0.90 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Part of Panathady Panchayat |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-kasaragod district-Panathady Panchayat-Water supply scheme to Panathady and Kallar Phase II |
Project Division Kannur ( KGD) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
25 Aug 2022 |
Work completed FCC submitted. |
Kanhangad Proj Dn AEE - 1 |
|
16 Aug 2022 |
Work completed FCC submitted. |
Kanhangad Proj Dn AEE - 1 |
|
21 Feb 2022 |
Work completed, FCC submitted. |
Kanhangad Proj Dn AEE - 1 |
|
05 Jul 2021 |
720 no's of FHTCs are given
|
Kanhangad Proj Dn AEE - 1 |
|
31 Mar 2021 |
335 fhtcs given |
Kanhangad Proj Dn AEE - 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
09/10/2020 |
Scheduled date of Completion of the Project |
08 Feb 2021 |
Expected date of Completion |
31/12/2021 |
Processing Dates
AS Date |
21 Aug 2020 |
TS Date |
27 Aug 2020 |