Jal Jeevan Mission (JJM)-Road restoration from Naragampally bridge to Venoli-Road restoration of 1500m in Kalleppully-Venoli road; From Venoli at ch 3/800 to Naragampally bridge road at ch 5/300-Pipeline Work
Project |
Jal Jeevan Mission (JJM)-Road restoration from Naragampally bridge to Venoli-Road restoration of 1500m in Kalleppully-Venoli road; From Venoli at ch 3/800 to Naragampally bridge road at ch 5/300-Pipeline Work |
Project Code |
PKDJJM022215054 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Jal Jeevan Mission (JJM)-Road restoration from Naragampally bridge to Venoli-Road restoration of 1500m in Kalleppully-Venoli road; From Venoli at ch 3/800 to Naragampally bridge road at
ch 5/300-Pipeline Work |
Status |
On-going |
District |
Palakkad |
Executing Office |
Palakkad Revenue Sn |
AS Amount (Rs) |
31700000
|
AS Number |
G.O.(RT)No.134/2022/WRD |
TS Amount (Rs) |
3435700 |
TS Number |
13660/2023-24 |
Total Bill Submitted (Rs) |
0 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
300 |
Capacity in MLD |
12.50 |
Actual Project Completion Date |
25 Mar 2024 |
Coverage |
Kalleppully-Venoli |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
Jal Jeevan Mission (JJM)-Road restoration from Naragampally bridge to Venoli-Road restoration of 1500m in Kalleppully-Venoli road; From Venoli at ch 3/800 to Naragampally bridge road at ch 5/300-Pipeline Work Sl |
Palakkad Revenue Sn |
|
No status have been added to this project
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
11/10/2023 |
Scheduled date of Completion of the Project |
31 Jan 2024 |
Expected date of Completion |
25/03/2024 |
Processing Dates
AS Date |
23 Feb 2022 |
TS Date |
12 Sep 2023 |