CENT.SPONSD ACCELERATED RWS SCHEME-PLAN(10)-ARWSS to West Kallada, Sooranad South and Sasthamcotta Pt. (1558)I
Project Code
KLMGOI1114485
Type
Main project
Funding Agency
GOI
Category
ARP Central
Type of scheme
Water Supply
Scheme
Description
WORK FULLY COMPLETED ON NOVEMBER 2020
Status
Completed
District
Kollam
Executing Office
Kollam Project Dn
AS Amount (Rs)
111500000
AS Number
TS Amount (Rs)
TS Number
Total Bill Submitted (Rs)
68110500
Total Bill Paid (Rs)
67710511
Population Benefitted
11000
Capacity in MLD
Actual Project Completion Date
Date is not specified
Coverage
Population covered-20000
Total kilometer of line laid-250DI-5200m
200mm DI K9-3612m
Packages
No.
Project Name
Location
View
1
CWSS To WEST KALLADA SASTHAMCOTTA AND SOORANAD SOUTH PANCHAYATHSupply and erection of clear water pumpsets at KakkakunnuS – PHASE 11 Supply and erection of clear water pumpsets at Kakkakunnu
Kollam Project Dn
2
Distribution main from Kakkakunnu OHSR to KCT Jn (250mm DI K9) - Connected to existing 200mm AC Pipe - in Sooranadu South Panchayath Distribution main from Kakkakunnu OHSR to Patharam HS Jn (250mm DI K9) - Connected to existing 200mm AC Pipe - in Sooranadu South Panchayath