AMRUT-Chavakkad Muncipality- AMRUT 2--Pipeline Work -Supplying and laying of distribution network and providing FHTCs-Pipeline Work
Project |
AMRUT-Chavakkad Muncipality- AMRUT 2--Pipeline Work -Supplying and laying of distribution network and providing FHTCs-Pipeline Work |
Project Code |
TCRAMRUT 2032314652 |
Type |
Main project |
Funding Agency |
AMRUT 2 |
Category |
AMRUT 2 |
Type of scheme |
Water Supply |
Scheme |
|
Description |
AMRUT-Chavakkad Municipality- AMRUT 2--Pipeline Work -Supplying and laying of distribution network and providing FHTCs-Pipeline Work |
Status |
On-going |
District |
Thrissur |
Executing Office |
Thrissur PH Dn |
AS Amount (Rs) |
120700000
|
AS Number |
G.O.(Rt)No.677/2023/LSGD |
TS Amount (Rs) |
117840000 |
TS Number |
WRD/KWA-CE(CR)/EST_TS/9523/2023_26_1_1 Dated: 09-05-2023 |
Total Bill Submitted (Rs) |
4925320 |
Total Bill Paid (Rs) |
4925320 |
Population Benefitted |
25000 |
Capacity in MLD |
13.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Chavakkad Municipality |
Packages
No. |
Project Name |
Location |
View |
1 |
AMRUT-Chavakkad Muncipality- AMRUT 2--Pipeline Work -Supplying and laying of distribution network and providing FHTCs-Pipeline Work |
Guruvayur PH Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
13 May 2024 |
1725 connections are tagged, and balance work ongoing |
Guruvayur PH Sn AE |
|
09 May 2024 |
1703 connections are tagged, and balance work ongoing |
Guruvayur PH Sn AE |
|
07 May 2024 |
1680 connections are tagged, and balance work ongoing
|
Guruvayur PH Sn AE |
|
03 May 2024 |
1653 connections are tagged, and balance work ongoing |
Guruvayur PH Sn AE |
|
29 Apr 2024 |
1550 connections are tagged, and balance work ongoing
|
Guruvayur PH Sn AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
13/07/2023 |
Scheduled date of Completion of the Project |
12 Jul 2024 |
Expected date of Completion |
12/07/2024 |
Processing Dates
AS Date |
21 Mar 2023 |
TS Date |
09 May 2023 |