AMRUT 2.0 - SWAP- 3

Project AMRUT 2.0 - SWAP- 3
Project Code IDKAMRUT112417202
Type Main project
Funding Agency AMRUT
Category AMRUT 2
Type of scheme Water Supply
Scheme AMRUT
Description Providing distribution network and FHTCs for Kattappana Municipality-Phase II
Status On-going
District Idukki
Executing Office Kattappana Project Dn
AS Amount (Rs) 206000000
AS Number G.O.(Rt)No.2263/2024/LSGD
TS Amount (Rs) 203800000
TS Number WRD/KWA-CE(CR)/EST_TS/4749/2024_26_1_1
Total Bill Submitted (Rs)
Total Bill Paid (Rs)
Population Benefitted 16000
Capacity in MLD 12.00
Actual Project Completion Date Date is not specified
Coverage Kattappana Municipality

Packages

No. Project Name Location View
1 Providing distribution network and FHTCs for Kattappana Municipality-Phase II Project Division Kattapana

Overall Project Status

Status Date Overall Project Status Project Officer Contact
05 Jun 2026 work ongoing Kattappana AEE 1
01 Jun 2026 work ongoing Kattappana AEE 1
28 May 2026 work ongoing Kattappana AEE 1
25 May 2026 work ongoing Kattappana AEE 1
22 May 2026 work ongoing Kattappana AEE 1

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 16/02/2025
Scheduled date of Completion of the Project 23 Dec 2026
Expected date of Completion 31/12/2026

Processing Dates

AS Date 22 Nov 2024
TS Date 17 Feb 2025

Other details

Project Officers View