DEPOSIT WORK - Supplying and laying 90mm pvc pipe and providing public taps at various places in Varkala Municipality
Project |
DEPOSIT WORK - Supplying and laying 90mm pvc pipe and providing public taps at various places in Varkala Municipality |
Project Code |
TVMDEPO032011794 |
Type |
Main project |
Funding Agency |
DEPO |
Category |
Deposit Work |
Type of scheme |
Water Supply |
Scheme |
DEPO |
Description |
Deposit work-Supplying and laying 90mm pvc pipe and providing public taps at various places in Varkala Municipality |
Status |
Completed |
District |
Thiruvananthapuram |
Executing Office |
Varkala WS Sn 1 |
AS Amount (Rs) |
1617000
|
AS Number |
PW3-3449/22 |
TS Amount (Rs) |
1617000 |
TS Number |
TS/2022-2023/2022/734 |
Total Bill Submitted (Rs) |
1058875 |
Total Bill Paid (Rs) |
0 |
Population Benefitted |
500 |
Capacity in MLD |
0.04 |
Actual Project Completion Date |
26 Oct 2022 |
Coverage |
Locations of work : 1) Varuvila road -300m, vilayil road -170m, Pillaveedu road - 100m, Therikkalkunnu temple road - 240m, Poikayilkulam road -300m, Kallamkonam Thazhebhagam - 90m, nadayara Kunnilkonam road - 150m, Olippuvila by lane - 90m |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
DEPOSIT WORK - Supplying and laying 90mm pvc pipe and providing public taps at various places in Varkala Municipality |
Varkala WS Sn 1 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
17 Jan 2023 |
Bill submitted to subdivision |
Varkala WS Sn - 1 AE |
|
23 Nov 2022 |
Work completed. Bill under preparation.
|
Varkala WS Sn - 1 AE |
|
31 Oct 2022 |
Work completed |
Varkala WS Sn - 1 AE |
|
28 Oct 2022 |
Work completed |
Varkala WS Sn - 1 AE |
|
27 Oct 2022 |
work completed |
Varkala WS Sn - 1 AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
12/10/2022 |
Scheduled date of Completion of the Project |
26 Oct 2022 |
Expected date of Completion |
26/10/2022 |
Processing Dates
AS Date |
18 Apr 2022 |
TS Date |
25 May 2022 |