State Plan 2022-23Supply and installation of off-grid inverter type solar power plant including 5KVA or more capacity 120 V in WTP, Maneed for internal and external lighting.

Project State Plan 2022-23Supply and installation of off-grid inverter type solar power plant including 5KVA or more capacity 120 V in WTP, Maneed for internal and external lighting.
Project Code EKMGOK052211987P1
Type Package
Main Project State Plan 2022-23 Supply and installation of off-grid inverter type solar power plant including 5KVA or more capacity 120 V in WTP, Maneed for internal and external lighting.
Funding Agency GOK
Category State plan
Type of scheme Water Supply
Scheme 2215-02-106-97
Description State Plan 2022-23Supply and installation of off-grid inverter type solar power plant including 5KVA or more capacity 120 V in WTP, Maneed for internal and external lighting.
Status On-going
District Ernakulam
Executing Office Piravam PH Sn
Agreement Number
Agreement Date
TS Amount (Rs) 800000
TS Number 11923/2022-2023
Technical specification NIL

No project review have been added to this project

Project Progress Status

Project Progress Status

Agreement Details

No Status Updated

Duration & Sanction dates

Date of start of Package 25/10/2022
Scheduled date of Completion as per agreement 11 Dec 2022
Expected date of Completion 31/03/2023

Processing Dates

TS Date 01 Sep 2022
Estimate Approval 01 Sep 2022
NIT Approval 01 Sep 2022
Tender Closing 28 Sep 2022
Technichal Pre-Qualification 01 Sep 2022
Price bid opening 30 Sep 2022

Approval Dates

Workorder Date 12 Oct 2022
NA 25 Oct 2022

Other details

Project Schedule View
Project Components View
Project Officers View

Project Status Updations See All Status Updations

Muvattupuzha PH Dn EE
Date: 02/03/2023

Work has been completed | 100% Completed

work completed.

Muvattupuzha PH Dn EE
Date: 01/03/2023

Work has been completed | 100% Completed

work completed.