Project |
JJM-Setting up New Sub District Lab at the first floor of Kayamkulam KWA Section Office |
Project Code |
KLMJJM09218468 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
JJM-Setting up New Sub District Lab at the first floor of Kayamkulam KWA Section Office |
Status |
On-going |
District |
Pathanamthitta |
Executing Office |
Alappuzha QC Sn |
AS Amount (Rs) |
11100000
|
AS Number |
GO(Rt) No. 489/2021/WRD |
TS Amount (Rs) |
5000000 |
TS Number |
TS/2021-2022/2021/24631 |
Total Bill Submitted (Rs) |
|
Total Bill Paid (Rs) |
|
Population Benefitted |
|
Capacity in MLD |
|
Actual Project Completion Date |
Date is not specified |
Coverage |
|
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-Setting up New Sub District Lab at the first floor of Kayamkulam KWA Section Office |
Alappuzha QC Sn |
|
2 |
- JJM- Setting up of Sub District Lab Kayamkulam at 1st floor of kwa office at Kayamkulam Alappuzha-Additional work for accrediation to bactereology |
Alappuzha QC Sn |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
12 Jun 2023 |
Work completed bill submitted |
Alappuzha QC AE |
|
17 May 2023 |
Work completed Bill Submitted |
Alappuzha QC AE |
|
08 May 2023 |
Work has been completed final bill submitted |
Alappuzha QC AE |
|
04 May 2023 |
work has been completed Final bill submitted
|
Alappuzha QC AE |
|
24 Apr 2023 |
Work completed Bills submitted |
Alappuzha QC AE |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
27/11/2021 |
Scheduled date of Completion of the Project |
26 Feb 2022 |
Expected date of Completion |
Date is not specified |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
27 Oct 2021 |