Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Jal Jeevan Mission - 2020-21 - Phase II - Providing FHTCs in Kollengode Grama Panchayath in Palakkad District

Project Jal Jeevan Mission - 2020-21 - Phase II - Providing FHTCs in Kollengode Grama Panchayath in Palakkad District
Project Code PKDJJM10207145
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Jal Jeevan Mission - 2020-21 - Phase II - Providing FHTCs in Kollengode Grama Panchayath in Palakkad District
Status On-going
District Palakkad
Executing Office Nenmara Sn
AS Amount (Rs) 15900000
AS Number Go(Rt)no 777/2020/WRD
TS Amount (Rs) 7213000
TS Number TS/2020-2021/2021/2464
Total Bill Submitted (Rs) 15723584
Total Bill Paid (Rs) 15723584
Population Benefitted 9900
Capacity in MLD 2.00
Actual Project Completion Date 31 Aug 2021
Coverage Public tap users in Kollengode Grama panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 Jal Jeevan Mission - 2020-21 - Phase II - Providing 990 Nos. FHTCs in Kollengode Grama Panchayath in Palakkad District and pipeline extension - Part 1 Nenmara Sn
2 Jal Jeevan Mission - 2020-21 - Phase II - Providing 990 Nos. FHTCs in Kollengode Grama Panchayath in Palakkad District and pipeline extension - Part 2 Nenmara Sn

Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Nov 2021 updated Palakkad PH Dn EE

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 31/07/2022
Scheduled date of Completion of the Project 31 Mar 2021
Expected date of Completion 31/07/2022

Processing Dates

AS Date 27 Oct 2020
TS Date 28 Jan 2021

Other details

Project Officers View